A fraction of proposed data centers will get built. Utilities are wising up.

Brian Martucci | Source: Utility DIVE | Posted 05/16/2025

Keyword Tags:

One expert estimated that speculative interconnection requests were five to 10 times more than the number of actual data centers, but the scale of the problem remains elusive.


AI generated summary

The U.S. grid is currently inundated with numerous data center proposals, many of which are unlikely to be realized. This situation complicates planning for utilities and grid operators, as they face a significant discrepancy between interconnection requests and actual data center constructions. Experts estimate that for every data center built, there are five to ten requests, leading to challenges in accurately forecasting power demand. The RAND Corporation's projections for AI-sector power consumption by 2030 vary widely, with some estimates suggesting consumption could reach 347 GW, while others predict it to be under 100 GW. This uncertainty creates difficulties for utilities in determining which requests are legitimate and how to allocate resources effectively.

Utilities are adopting various strategies to manage the influx of speculative requests, including standardized interconnection processes and requiring larger financial commitments from developers. However, the lack of transparency in the development process, where developers often conceal their activities, exacerbates the issue. Some utilities are exploring new rate structures to ensure that data centers contribute fairly to infrastructure costs, while others are advocating for a standardized approach to interconnection that could reduce speculative requests. Despite these efforts, the challenge remains significant, as developers continue to leverage the system to secure advantageous positions in the interconnection queue.



Link to Original Article

Please find the link to the full article below. (Please note that content provider might require a paid subscription)


Source Link: https://www.utilitydive.com/news/a-fraction-of-proposed-data-centers-will-get-built-utilities-are-wising-up/748214/

Create a free trial account: Sign Up

Grid monitor is free to try. No credit card required


Already have an account? Login

Most Active PUCT Filings

APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE SETEX AREA RELIABILITY PROJECT IN JASPER, MONTGOMERY, NEWTON, POLK, SAN JACINTO, TRINITY, TYLER, AND WALKER COUNTIES - (195 filings)

APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (120 filings)

CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (115 filings)

BROKER REGISTRATIONS - (88 filings)

APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR APPROVAL OF ITS 2026-2028 TRANSMISSION AND DISTRIBUTION SYSTEM RESILIENCY PLAN - (70 filings)

CY 2024 ANNUAL POWER LINE INSPECTION & SAFETY REPORT IN PURSUANT TO 16 TAC § 25.97(F) - (59 filings)

PROJECT TO SUBMIT EMERGENCY OPERATIONS PLANS AND RELATED DOCUMENTS UNDER 16 TAC § 25.53 - (59 filings)