PUC Chair Proposes $2.4 Billion Hard Cap for Entergy's Gas Plants

DOUG LEWIN | Source: Doug Lewin | Posted 09/12/2025

Keyword Tags:

PUC Chairman Gleeson would like Entergy consumers to have some protection from rising costs; PUC issues RFI for Backup Power Packages; new records this week for both solar and storage


AI generated summary

At a recent Public Utility Commission (PUC) meeting, Chair Gleeson proposed a $2.4 billion hard cap for Entergy's two gas plants, which would limit costs to $2,000 per kilowatt. This proposal comes in response to Entergy's lack of consideration for alternative energy sources, placing the risk of cost overruns on customers without a cap. The hard cap aims to share some of that risk with Entergy, which operates as a monopoly utility outside of ERCOT.

Additionally, the PUC is moving forward with the Texas Backup Power Package Program, which will allocate $1.8 billion for backup power solutions at critical facilities. The program aims to enhance resilience during outages, offering incentives for microgrid installations. Meanwhile, solar energy production has reached new heights, with solar output nearing 30GW and battery discharge surpassing 7,500 megawatts, indicating significant advancements in renewable energy capacity in the region.



Link to Original Article

Please find the link to the full article below. (Please note that content provider might require a paid subscription)


Source Link: https://www.douglewin.com/p/puc-chair-proposes-hard-cap-for-entergy

Create a free trial account: Sign Up

Grid monitor is free to try. No credit card required


Already have an account? Login

Most Active PUCT Filings

CY 2024 RETAIL ELECTRIC PROVIDER (REP) ANNUAL REPORTS AND CY 2025 REP SEMI-ANNUAL REPORTS PURSUANT TO 16 TAC 25.107(I) - (98 filings)

CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (93 filings)

APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (88 filings)

BROKER REGISTRATIONS - (76 filings)

APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (62 filings)

APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (52 filings)

APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE DIVISION 138-KV TRANSMISSION LINE IN TARRANT AND DALLAS COUNTIES - (49 filings)