Entergy: Texas Celebrates Completion of $110 Million Bolivar Peninsula Reliability Project
Matthew Bennett | Source: Entergy Newsroom | Posted 09/05/2025

BOLIVAR PENINSULA, Texas – A promise made to the Bolivar Peninsula community is now a promise kept. Entergy Texas completed construction on a $110 million reliability project that doubles the region’s power supply and strengthens the Southeast Texas power grid. Launched less than three years ago, the Bolivar Peninsula Reliability Project fulfills a commitment to provide more reliable service, reduce outages, and better protect the coastal community from the impacts of increasingly severe weather.
AI generated summary
Entergy Texas has successfully completed the $110 million Bolivar Peninsula Reliability Project, which aims to enhance the power supply and strengthen the Southeast Texas power grid. This initiative, launched less than three years ago, was designed to provide more reliable service, reduce outages, and protect the coastal community from severe weather impacts. CEO Eliecer Viamontes emphasized the importance of collaboration with the Bolivar community to address their challenges and deliver meaningful improvements.
The project includes the construction of two new substations, upgrades to three existing substations, and approximately 25 miles of new distribution lines. Additionally, it features self-healing network technology and composite poles built to withstand extreme weather. The effectiveness of these upgrades was demonstrated during Hurricane Beryl in 2024, where the new infrastructure performed well, allowing for quicker power restoration and minimal maintenance needs. This project is part of Entergy Texas' broader efforts to modernize the power grid in one of the state's fastest-growing regions.
Link to Original Article
Please find the link to the full article below. (Please note that content provider might require a paid subscription)
Source Link: https://www.entergy.com/news/entergy-texas-celebrates-completion-of-110-million-bolivar-peninsula-reliability-project
09/08 - 9:30 AM
ERCOT - RTCB Market Trials Weekly Webex09/08 - 10:00 AM
PUCT - Comments Due Project No. 5848409/09 - 3:00 PM
ERCOT - RMS Meeting09/09 - 9:30 AM
09/06/2025
US utilities have committed to 116 GW of large load capacity growth, equal to 15.5% of current US peak demand09/06/2025
Coal Is Rising Along with Solar in the U.S. Power System, While Gas Loses a Step09/06/2025
FERC in Focus: Will the agency maintain its independence under Trump 2.0?09/06/2025
Electric Deregulation Historically Means Higher Power Bills09/05/2025
Entergy: Texas Celebrates Completion of $110 Million Bolivar Peninsula Reliability ProjectCY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (117 filings)
CY 2024 RETAIL ELECTRIC PROVIDER (REP) ANNUAL REPORTS AND CY 2025 REP SEMI-ANNUAL REPORTS PURSUANT TO 16 TAC 25.107(I) - (107 filings)
APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (87 filings)
APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (80 filings)
BROKER REGISTRATIONS - (68 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (56 filings)
AGGREGATOR ANNUAL REPORTS - (44 filings)