Oncor has 200 GW of interconnection requests, company officials say
Emma Penrod | Source: Utility DIVE | Posted 08/12/2025

About 20% of the potential demand has signed contracts or is considered “high-confidence load,” CEO Allen Nye said.
AI generated summary
Oncor Electric Delivery currently has approximately 200 GW of interconnection requests, which include significant contributions from data centers, traditional commercial and industrial customers, cryptocurrency facilities, and oil and gas operations. CEO Allen Nye indicated that around 20% of this demand has either signed contracts or is classified as 'high-confidence load.' This surge in interconnection requests could lead Oncor to revise its capital plan, potentially adding over $12 billion to its existing $36 billion plan.
Sempra's strategy to focus more on utility operations, driven by the increasing electric demand in Oncor's service area, is expected to enhance earnings and mitigate risks for investors. The company is also in the process of selling stakes in its Ecogas Mexico and Sempra Infrastructure, which are anticipated to close by mid-2026. These sales aim to bolster Oncor's expansion efforts, with Sempra expecting a greater share of its earnings to come from regulated utilities, particularly in Texas, as Oncor continues to grow its customer base and interconnection agreements.
Link to Original Article
Please find the link to the full article below. (Please note that content provider might require a paid subscription)
Source Link: https://www.utilitydive.com/news/oncor-sempra-interconnection-texas-data-center-earnings/757262/
08/12 - 9:00 AM
ERCOT - Biennial TAC Stakeholder Body Structural and Procedural Review - Webex Only08/12 - 9:30 AM
ERCOT - PRS Meeting08/13 - 9:30 AM
ERCOT - SSWG Tuning Training - Webex Only08/13 - 9:30 AM
08/12/2025
08/12/2025 Biennial TAC Stakeholder Body Structural and Procedural Review08/12/2025
Oncor has 200 GW of interconnection requests, company officials say08/12/2025
Nuclear regulatory approval drives NuScale customer interest, but no deals yet08/12/2025
Texas HyperGrid: Hope Or Hype?08/12/2025
Ethereum Miners in Texas Use Renewable Energy to Cut Costs and Boost Grid StabilityAPPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (132 filings)
APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (116 filings)
BROKER REGISTRATIONS - (83 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (59 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR DETERMINATION OF SYSTEM RESTORATION COSTS - (46 filings)
CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (46 filings)
APPLICATION OF SHARYLAND UTILITIES, L.L.C. FOR AUTHORITY TO CHANGE RATES - (43 filings)