Rapid Demand Growth Outpaced by New Supply in Texas
DOUG LEWIN | Source: Doug Lewin | Posted 08/06/2025

EIA projects 14% electric demand growth in Texas in 2026; Texas now installing nearly two gigawatts of supply per month; 150% increase in gas plants in the queue; PUC reveals SB 6 implementation plans
AI generated summary
The Energy Information Administration (EIA) projects a remarkable 14% annual demand growth in the Electric Reliability Council of Texas (ERCOT), with consumption expected to rise from approximately 400 terawatt-hours in 2021 to nearly 500 terawatt-hours by 2025. This growth rate, which has not been seen since the 1960s, is being met with an impressive increase in supply, as ERCOT synchronized an additional 1.9 gigawatts of capacity to the grid in July alone. The new supply consists of solar, storage, and wind energy, reflecting a significant acceleration in the pace of capacity additions in Texas.
In addition to the immediate supply increases, ERCOT has a substantial queue of over 430 gigawatts of additional capacity awaiting interconnection. This includes significant amounts of solar, battery storage, wind, and gas. The growth of renewable energy and gas capacity in Texas is unparalleled in the country, positioning ERCOT to effectively manage the anticipated demand surge. Furthermore, the Public Utility Commission (PUC) is actively working on several dockets related to Senate Bill 6, which aims to address various operational and regulatory challenges, including net metering for large loads and demand response programs for large users.
Link to Original Article
Please find the link to the full article below. (Please note that content provider might require a paid subscription)
Source Link: https://www.douglewin.com/p/rapid-demand-growth-outpaced-by-new
08/07 - 8:30 AM
ERCOT - ROS Meeting08/07 - 9:30 AM
PUCT - ERCOT Bond Open Meeting08/08 - 9:30 AM
LEGE - Senate Disaster Preparedness & Flooding, Select08/08 - 9:00 AM
08/06/2025
08/06/2025 WMS Meeting08/06/2025
Energy Department Announces First Pilot Project for Advanced Nuclear Fuel Lines08/06/2025
Texas transmission line reroute PUC debate delays decision again08/06/2025
Rapid Demand Growth Outpaced by New Supply in Texas08/06/2025
Wave energy’s huge potential could finally be unlocked by the power of soundAPPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (105 filings)
APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (95 filings)
BROKER REGISTRATIONS - (87 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (65 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR DETERMINATION OF SYSTEM RESTORATION COSTS - (57 filings)
APPLICATION OF SHARYLAND UTILITIES, L.L.C. FOR AUTHORITY TO CHANGE RATES - (51 filings)
PROJECT TO SUBMIT EMERGENCY OPERATIONS PLANS AND RELATED DOCUMENTS UNDER 16 TAC § 25.53 - (39 filings)