Texas utility shuffling location of temporary emergency generation units to address regional power shortfall

Paul Gerke | Source: Renewable Energy World | Posted 06/25/2025

Keyword Tags:

We’re just a few days removed from the official start of summer, and it’s already shaping up to be a scorcher in many parts of the United States. While the eastern half of the country sweats out a stretch of dangerous heat and humidity, a major Texas utility is preparing for what’s to come.


AI generated summary

As summer begins, CenterPoint Energy is proactively addressing a potential power shortfall in the San Antonio region of Texas by relocating temporary emergency generation units from the Greater Houston area. The utility has dispatched the first five of 15 large units, each capable of powering around 30,000 homes, to help meet the increased energy demands expected this summer. These units, which will be deployed in waves over the next two months, are part of a collaborative effort with the Electric Reliability Council of Texas (ERCOT) and other stakeholders, following lessons learned from past energy crises.

In addition to enhancing reliability, the deployment of these generators is expected to lower energy bills for Houston-area customers. CenterPoint Energy has assured that it will not profit from the operation of these units in San Antonio, as per its agreement with ERCOT. To help customers prepare for the heat, CenterPoint is also offering energy-saving tips, such as adjusting thermostats, maintaining HVAC systems, and using energy-efficient appliances, to promote energy conservation and cost savings during the hot months ahead.



Link to Original Article

Please find the link to the full article below. (Please note that content provider might require a paid subscription)


Source Link: https://www.renewableenergyworld.com/power-grid/outage-management/texas-utility-shuffling-location-of-temporary-emergency-generation-units-to-address-regional-power-shortfall/

Create a free trial account: Sign Up

Grid monitor is free to try. No credit card required


Already have an account? Login

Most Active PUCT Filings

APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (150 filings)

BROKER REGISTRATIONS - (79 filings)

PROJECT TO SUBMIT EMERGENCY OPERATIONS PLANS AND RELATED DOCUMENTS UNDER 16 TAC § 25.53 - (47 filings)

APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR DETERMINATION OF SYSTEM RESTORATION COSTS - (44 filings)

APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (41 filings)

CY 2025 ELECTRIC UTILITY TRANSMISSION CONSTRUCTION REPORTS UNDER 16 TAC § 25.83 - (33 filings)

INFORMATIONAL FILING OF ERCOT INTERCONNECTION AGREEMENTS PURSUANT TO SUBST. R. §25.195(e) - (32 filings)