Gas turbine manufacturers expand capacity, but order backlog could prove stubborn

Diana DiGangi | Source: Utility DIVE | Posted 09/09/2025

Keyword Tags:

One expert said the industry moves are unlikely to “drastically reduce” wait times, which can stretch as long as seven years.


AI generated summary

Mitsubishi Heavy Industries is set to double its gas turbine manufacturing capacity within two years to meet rising demand and a growing backlog of orders, as reported by Bloomberg. The average delivery wait time for gas turbines has recently stretched to several years. Other manufacturers, such as GE Vernova and Siemens Energy, are also expanding their production capabilities, with GE investing $41 million to enhance its generator manufacturing and Siemens adding 61,000 square feet to its facility for turbine components. Despite these expansions, experts suggest that the increased output may not significantly reduce wait times due to the complexity of manufacturing and labor requirements.

The surge in demand for gas turbines is largely driven by the need to replace aging infrastructure and the rapid growth of data centers. Siemens Energy reported that 65% of its gas turbine orders this fiscal year have come from data centers, highlighting a shift in market dynamics. While there is optimism about the sustainability of increased production, experts caution that long-term demand remains uncertain, drawing parallels to past fluctuations in the natural gas market. Factors such as coal retirements and the growing energy needs of data centers are expected to influence gas turbine demand through 2025.



Link to Original Article

Please find the link to the full article below. (Please note that content provider might require a paid subscription)


Source Link: https://www.utilitydive.com/news/mitsubishi-gas-turbine-manufacturing-capacity-expansion-supply-demand/759371/

Create a free trial account: Sign Up

Grid monitor is free to try. No credit card required


Already have an account? Login

Most Active PUCT Filings

CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (114 filings)

CY 2024 RETAIL ELECTRIC PROVIDER (REP) ANNUAL REPORTS AND CY 2025 REP SEMI-ANNUAL REPORTS PURSUANT TO 16 TAC 25.107(I) - (106 filings)

APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (76 filings)

APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (73 filings)

BROKER REGISTRATIONS - (71 filings)

APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (53 filings)

AGGREGATOR ANNUAL REPORTS - (43 filings)