Meeting Summary - 05/20/2025 RPG Meeting
Grid Monitor AI | Posted 05/20/2025

▶️1 - Antitrust Admonition - 9:30 a.m.
▶️2 - Miscellaneous Updates
- No updates were presented during this agenda item.
- No participants raised their hands or made comments in the queue.
▶️3 - EIR Status Update – Baytown Area Load Addition Project
EIR-CNP-Baytown_Area_Load_Addition_Project_May_RPG.pdf
- Ben Richardson from ERCOT presented the status update on the CenterPoint Baytown area load addition project.
- The project is a $141 million, tier one project due to a 500 MVA load addition in the Baytown area.
- Previous meetings addressed the project scope, and the current meeting focused on additional findings.
- Options 2 and 2A involve addressing overloads discovered in initial assessments and maintenance evaluations.
- Option 3 considers bringing in 345-kV lines from Sheldon to Baytown for substation benefits.
- A finalized recommendation is aimed for Q2 2025, following the completion of option two a.
- Discussion on load scaling was raised regarding the inclusion of new flexible loads and how historical data is used.
- The necessity of studying load clusters versus individual loads was addressed, with project submissions often determining clustering.
- Procedures were discussed on the financial responsibilities of load customers, including securitization versus rate basing of upgrades.
4 - EIR Status Update – Texas A&M University System RELLIS Campus Reliability Project
- Not Discussed
▶️5 - EIR Status Update – Roscoe Area Upgrades Project
EIR-Oncor-Roscoe-Area-Upgrades-Project-StatusUpdate-May_2025_RPG.pdf
- Presenter: Abishek Penti provided a status update on the Oncor Roscoe area upgrades project.
- Project Overview: Oncor submitted the Roscoe area upgrades for RPG review in December 2024, a tier two project with an estimated cost of around $83 million, requiring a CCN with an expected service date of June 2028.
- Project Purpose: Address voltage violations as identified by Oncor.
- Project Scope: Involves construction and upgrade activities, including a new Oak Spring station, auto transformers, line upgrades, and decommissioning and rebuilding of certain lines.
- Study Overview: Used 2024 RTP data and updated loads for the study base case.
- Preliminary Results: ERCOT identified voltage violations and power flow violations and assessed four different options, deeming options one and four for further evaluation.
- Maintenance Outage Evaluation: Shortlisted options did not show voltage, thermal, or power flow violations.
- Load Serving Capability: Both options improved operational flexibility with option four slightly better.
- Cost Estimates: Option one estimated at $84.3 million and option four at $133.4 million, both requiring CCN.
- Preferred Option: Option one selected due to addressing project needs, meeting reliability criteria, being cost-effective, and improving long-term load capacity.
- Congestion Analysis: No new congestion identified within the study area for the preferred option.
- Next Steps: EIR report to be posted in the MIS by May.
- Q&A: Discussed assumptions regarding flexible loads and transfer capability.
▶️6 - Muscovy and Voss Lake 345/138-kV Project Overview
Oncor_Muscovy_Voss-Lake_RPG_05202025.pdf
- Overview of the Muscovy and Voss Lake 345/138-kV project presented.
- Joint project with Oncor and LCRA TSC.
- Tier one project located in Williamson and Milam Counties.
- Project aims to resolve thermal violations, provide additional 345-kV sources, further network transmission facilities, and enhance system reliability.
- Total combined cost for Oncor and LCRA TSC is just under $382,000,000.
- Project includes installation of three new 345/138-kV autotransformers, one 10.4 Mvar capacitor bank, and new transmission lines.
- 29 miles of new 345-kV double circuit transmission lines and 2 miles of new 345-kV transmission lines to be installed.
- Highlight of existing configuration reveals thermal violations mainly at Hutto and Sandow switches due to significant load growth.
- Oncor to establish a new Muscovy 345/138-kV switch east of Limmer and Teal Switch, with breaker and a half arrangement.
- Construction of Voss Lake 345/138-kV switch north of Sandow with one auto transformer.
- Construct 25-mile 345-kV double circuit line from Muscovy to Voss Lake rated 5,000 amps.
- Construct 2-mile 345-kV line from Voss Lake to Walleye Creek as a single circuit on double circuit capable structures.
- Coordinate construction of a 4-mile 345-kV double circuit line from Limmer to Muscovy rated 5,000 amps.
- No questions were raised after the presentation.
▶️7 - ERCOT Independent Review Scope: Muscovy and Voss Lake 345/138-kV Project
EIR-Oncor-and-LCRA-TSC-Muscovy-Voss-_SCOPE_May2025_RPG.pdf
- Presenter Abishek Penti gave an overview of the project's scope for Oncor and LCRA TSC's Muscovy and Voss Lake 345/138-kV project.
- Project classified as tier one with an estimated cost of $381,830,000 and an estimated in-service date of December 2028.
- The project's main purpose is to address reliability violations identified by Oncor and LCRA.
- Independent review is underway with the use of 2024 RTP 2029 summer peak case as a seed for the study base case.
- Consideration of transmission projects with in-service dates on or before December 1, 2028. Other placeholder projects from RTP 2024 will be removed.
- Evaluation criteria include thermal ratings, voltage limits, and contingencies P0 to P6 and G-1 and X-1 evaluations on specified generators and autotransformers.
- Study procedure involves need analysis, project alternatives testing, planned maintenance outage, and long-term load serving capability assessments.
- Congestion analysis and potential sensitivity analyses might be performed as per relevant sections of the planning guide.
- Final recommendations are expected by the end of Q3 2025.
- Discussion addressed questions on potential inclusion of 765-kV import lines in independent reviews; deemed unlikely due to timelines.
▶️8 - 2026 Long-Term System Assessment (LTSA) Planning
Presenter: Pengwei Du from ERCOT
- Evaluating potential needs of ERCOT's high voltage system (345-kv and 765-kv) for 10-15 years out.
- Strategic guidance for the six-year planning process.
- Utilization of multiple scenarios to explore future outcomes based on different sensitivities and key factors.
Key Planning Aspects
- Stakeholder engagement process initiated for feedback on key assumptions and scenarios.
- Current trend scenario as a baseline, with additional scenarios to represent different load growth trajectories.
- Biannual process with report completion expected by December 31, 2026.
Key Assumptions
- Adjusted load forecast reflecting adjustments applied to TSP provider larger load addition.
- Moderate growth assumptions for rooftop PV and electric vehicles (EV).
- Carbon price assumed at $0 per ton with no EPA rules impact for coal and gas units.
- Economic retirement is considered instead of fixed age retirement.
Large Flexible Load (LFL) Assumptions
- 60% of LFL has a strike price at $100/MWh.
- 30% of LFL responds at $200/MWh.
- 10% of LFL has a strike price at $1,000/MWh.
Capacity Expansion Analysis
- Built upon starting generation portfolio including existing and planned resources that meet Planning Guide Section 6.9(1) requirements.
- Determination of additions of new resources and economic retirement of existing generation fleet.
Questions and Discussions
John Snyder: Study years for LTSA include ten and fifteen years out, focusing on transmission needs for years 2036 and 2041.
Prabhu Gnanam: Transmission modeling based on RTP findings; base cases include approved projects by the commission.
Xuan Wu: Transverse stability will not be studied in LTSA but will be examined in annual planning assessments.
Shuye Teng:
- Regarding Generation Retirement: Fixed age retirement removed due to inconsistencies; open to discussing adjustments.
- Regarding Large Flexible Load: Assumptions based on actual responses and 2010 feedback from large load owners.
- Environmental Policy Assumptions: Scenarios in the past may vary; intention to capture policy variations in future scenarios.
▶️9 - Weather Year Selection Methodology Updates for 2025 Regional Transmission Plan (RTP) Economic Study
Weather_Year_Selection_Update_Final.pdf
- Nelson Avila presented updates to the weather year selection methodology for the 2025 RTP economic study.
- The weather year selection is crucial as it determines renewable and load profiles for production cost simulation.
- Prior to 2017, ERCOT used a single weather year representing the average of 16 available years.
- In 2017, ERCOT developed a methodology to include sensitivity weather years to address weather uncertainties.
- The updated methodology now incorporates peak net load and net load demand variables, improving risk capture during peak net load hours.
- New metrics now include correlation with location of wind and solar units.
- Weather years are now ranked with different scores separating load and renewables compared to the previous single-scoring method.
- Flexibility is introduced to select weather years specific to constraints related to renewable generation patterns.
- Stakeholder feedback is sought on the new methodology.
- Variables used in the new methodology include peak load, demand load, peak net load, and demand of net load.
- Renewable generation variables include correlated metrics for wind and solar capacity factors.
- A final score is created by averaging renewable and load scores, helping to rank weather years on a heat map.
- A difference with the previous methodology is the ranking order of load variables (descending) versus renewable variables (ascending).
- Sensitivity weather years are selected to focus on known constraints like Panhandle and West Texas exports.
- Question and answer session included queries about distinctions between peak and net load, the methodology's applicability to reliability studies, and adjustments based on DER growth.
- ERCOT confirms the 2025 RTP methodology targets economic rather than reliability studies.
- Discussion continues on the application of the new methodology to other constraints and potential timeline for implementation.
- ERCOT emphasizes that stakeholder feedback will be considered before finalizing the methodology.
▶️10 - Adjourn
08/14 - 3:00 PM
ERCOT - OTWG Meeting - Webex Only08/14 - 9:00 AM
ERCOT - Texas SET Meeting08/14 - 9:30 AM
ERCOT - LLWG Meeting08/14 - 9:30 AM
08/14/2025
08/13/2025 PWG Meeting08/14/2025
Flexibility as a Service with Octopus Energy US CEO Nick Chaset08/14/2025
Microgrid Market to Reach US$ 163.17 Billion by 2033, Driven by Energy Independence and Rural Electrification08/14/2025
Multidirectional flows of power and information are the grid’s future08/14/2025
How one Texas solar company cut engineering and permitting time from 40 days to fourAPPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (138 filings)
APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (115 filings)
CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (103 filings)
BROKER REGISTRATIONS - (88 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (72 filings)
CY 2024 RETAIL ELECTRIC PROVIDER (REP) ANNUAL REPORTS AND CY 2025 REP SEMI-ANNUAL REPORTS PURSUANT TO 16 TAC 25.107(I) - (57 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR DETERMINATION OF SYSTEM RESTORATION COSTS - (46 filings)