Meeting Summary - 05/20/2025 RPG Meeting
Grid Monitor AI | Posted 05/20/2025

▶️1 - Antitrust Admonition - 9:30 a.m.
▶️2 - Miscellaneous Updates
- No updates were presented during this agenda item.
- No participants raised their hands or made comments in the queue.
▶️3 - EIR Status Update – Baytown Area Load Addition Project
EIR-CNP-Baytown_Area_Load_Addition_Project_May_RPG.pdf
- Ben Richardson from ERCOT presented the status update on the CenterPoint Baytown area load addition project.
- The project is a $141 million, tier one project due to a 500 MVA load addition in the Baytown area.
- Previous meetings addressed the project scope, and the current meeting focused on additional findings.
- Options 2 and 2A involve addressing overloads discovered in initial assessments and maintenance evaluations.
- Option 3 considers bringing in 345-kV lines from Sheldon to Baytown for substation benefits.
- A finalized recommendation is aimed for Q2 2025, following the completion of option two a.
- Discussion on load scaling was raised regarding the inclusion of new flexible loads and how historical data is used.
- The necessity of studying load clusters versus individual loads was addressed, with project submissions often determining clustering.
- Procedures were discussed on the financial responsibilities of load customers, including securitization versus rate basing of upgrades.
4 - EIR Status Update – Texas A&M University System RELLIS Campus Reliability Project
- Not Discussed
▶️5 - EIR Status Update – Roscoe Area Upgrades Project
EIR-Oncor-Roscoe-Area-Upgrades-Project-StatusUpdate-May_2025_RPG.pdf
- Presenter: Abishek Penti provided a status update on the Oncor Roscoe area upgrades project.
- Project Overview: Oncor submitted the Roscoe area upgrades for RPG review in December 2024, a tier two project with an estimated cost of around $83 million, requiring a CCN with an expected service date of June 2028.
- Project Purpose: Address voltage violations as identified by Oncor.
- Project Scope: Involves construction and upgrade activities, including a new Oak Spring station, auto transformers, line upgrades, and decommissioning and rebuilding of certain lines.
- Study Overview: Used 2024 RTP data and updated loads for the study base case.
- Preliminary Results: ERCOT identified voltage violations and power flow violations and assessed four different options, deeming options one and four for further evaluation.
- Maintenance Outage Evaluation: Shortlisted options did not show voltage, thermal, or power flow violations.
- Load Serving Capability: Both options improved operational flexibility with option four slightly better.
- Cost Estimates: Option one estimated at $84.3 million and option four at $133.4 million, both requiring CCN.
- Preferred Option: Option one selected due to addressing project needs, meeting reliability criteria, being cost-effective, and improving long-term load capacity.
- Congestion Analysis: No new congestion identified within the study area for the preferred option.
- Next Steps: EIR report to be posted in the MIS by May.
- Q&A: Discussed assumptions regarding flexible loads and transfer capability.
▶️6 - Muscovy and Voss Lake 345/138-kV Project Overview
Oncor_Muscovy_Voss-Lake_RPG_05202025.pdf
- Overview of the Muscovy and Voss Lake 345/138-kV project presented.
- Joint project with Oncor and LCRA TSC.
- Tier one project located in Williamson and Milam Counties.
- Project aims to resolve thermal violations, provide additional 345-kV sources, further network transmission facilities, and enhance system reliability.
- Total combined cost for Oncor and LCRA TSC is just under $382,000,000.
- Project includes installation of three new 345/138-kV autotransformers, one 10.4 Mvar capacitor bank, and new transmission lines.
- 29 miles of new 345-kV double circuit transmission lines and 2 miles of new 345-kV transmission lines to be installed.
- Highlight of existing configuration reveals thermal violations mainly at Hutto and Sandow switches due to significant load growth.
- Oncor to establish a new Muscovy 345/138-kV switch east of Limmer and Teal Switch, with breaker and a half arrangement.
- Construction of Voss Lake 345/138-kV switch north of Sandow with one auto transformer.
- Construct 25-mile 345-kV double circuit line from Muscovy to Voss Lake rated 5,000 amps.
- Construct 2-mile 345-kV line from Voss Lake to Walleye Creek as a single circuit on double circuit capable structures.
- Coordinate construction of a 4-mile 345-kV double circuit line from Limmer to Muscovy rated 5,000 amps.
- No questions were raised after the presentation.
▶️7 - ERCOT Independent Review Scope: Muscovy and Voss Lake 345/138-kV Project
EIR-Oncor-and-LCRA-TSC-Muscovy-Voss-_SCOPE_May2025_RPG.pdf
- Presenter Abishek Penti gave an overview of the project's scope for Oncor and LCRA TSC's Muscovy and Voss Lake 345/138-kV project.
- Project classified as tier one with an estimated cost of $381,830,000 and an estimated in-service date of December 2028.
- The project's main purpose is to address reliability violations identified by Oncor and LCRA.
- Independent review is underway with the use of 2024 RTP 2029 summer peak case as a seed for the study base case.
- Consideration of transmission projects with in-service dates on or before December 1, 2028. Other placeholder projects from RTP 2024 will be removed.
- Evaluation criteria include thermal ratings, voltage limits, and contingencies P0 to P6 and G-1 and X-1 evaluations on specified generators and autotransformers.
- Study procedure involves need analysis, project alternatives testing, planned maintenance outage, and long-term load serving capability assessments.
- Congestion analysis and potential sensitivity analyses might be performed as per relevant sections of the planning guide.
- Final recommendations are expected by the end of Q3 2025.
- Discussion addressed questions on potential inclusion of 765-kV import lines in independent reviews; deemed unlikely due to timelines.
▶️8 - 2026 Long-Term System Assessment (LTSA) Planning
Presenter: Pengwei Du from ERCOT
- Evaluating potential needs of ERCOT's high voltage system (345-kv and 765-kv) for 10-15 years out.
- Strategic guidance for the six-year planning process.
- Utilization of multiple scenarios to explore future outcomes based on different sensitivities and key factors.
Key Planning Aspects
- Stakeholder engagement process initiated for feedback on key assumptions and scenarios.
- Current trend scenario as a baseline, with additional scenarios to represent different load growth trajectories.
- Biannual process with report completion expected by December 31, 2026.
Key Assumptions
- Adjusted load forecast reflecting adjustments applied to TSP provider larger load addition.
- Moderate growth assumptions for rooftop PV and electric vehicles (EV).
- Carbon price assumed at $0 per ton with no EPA rules impact for coal and gas units.
- Economic retirement is considered instead of fixed age retirement.
Large Flexible Load (LFL) Assumptions
- 60% of LFL has a strike price at $100/MWh.
- 30% of LFL responds at $200/MWh.
- 10% of LFL has a strike price at $1,000/MWh.
Capacity Expansion Analysis
- Built upon starting generation portfolio including existing and planned resources that meet Planning Guide Section 6.9(1) requirements.
- Determination of additions of new resources and economic retirement of existing generation fleet.
Questions and Discussions
John Snyder: Study years for LTSA include ten and fifteen years out, focusing on transmission needs for years 2036 and 2041.
Prabhu Gnanam: Transmission modeling based on RTP findings; base cases include approved projects by the commission.
Xuan Wu: Transverse stability will not be studied in LTSA but will be examined in annual planning assessments.
Shuye Teng:
- Regarding Generation Retirement: Fixed age retirement removed due to inconsistencies; open to discussing adjustments.
- Regarding Large Flexible Load: Assumptions based on actual responses and 2010 feedback from large load owners.
- Environmental Policy Assumptions: Scenarios in the past may vary; intention to capture policy variations in future scenarios.
▶️9 - Weather Year Selection Methodology Updates for 2025 Regional Transmission Plan (RTP) Economic Study
Weather_Year_Selection_Update_Final.pdf
- Nelson Avila presented updates to the weather year selection methodology for the 2025 RTP economic study.
- The weather year selection is crucial as it determines renewable and load profiles for production cost simulation.
- Prior to 2017, ERCOT used a single weather year representing the average of 16 available years.
- In 2017, ERCOT developed a methodology to include sensitivity weather years to address weather uncertainties.
- The updated methodology now incorporates peak net load and net load demand variables, improving risk capture during peak net load hours.
- New metrics now include correlation with location of wind and solar units.
- Weather years are now ranked with different scores separating load and renewables compared to the previous single-scoring method.
- Flexibility is introduced to select weather years specific to constraints related to renewable generation patterns.
- Stakeholder feedback is sought on the new methodology.
- Variables used in the new methodology include peak load, demand load, peak net load, and demand of net load.
- Renewable generation variables include correlated metrics for wind and solar capacity factors.
- A final score is created by averaging renewable and load scores, helping to rank weather years on a heat map.
- A difference with the previous methodology is the ranking order of load variables (descending) versus renewable variables (ascending).
- Sensitivity weather years are selected to focus on known constraints like Panhandle and West Texas exports.
- Question and answer session included queries about distinctions between peak and net load, the methodology's applicability to reliability studies, and adjustments based on DER growth.
- ERCOT confirms the 2025 RTP methodology targets economic rather than reliability studies.
- Discussion continues on the application of the new methodology to other constraints and potential timeline for implementation.
- ERCOT emphasizes that stakeholder feedback will be considered before finalizing the methodology.
▶️10 - Adjourn
05/20 - 8:00 AM
LEGE - House 89th Legislative Session05/20 - 10:00 AM
LEGE - Senate Session05/20 - 11:00 AM
ERCOT - Texas SET Meeting - Webex Only05/20 - 9:30 AM
05/20/2025
Meeting Summary - 05/20/2025 PLWG Meeting05/20/2025
Meeting Summary - 05/20/2025 NDSWG Meeting05/20/2025
Meeting Summary - 05/20/2025 RPG Meeting05/20/2025
Meeting Summary - 05/19/2025 CMWG Meeting05/20/2025
Blackstone Acquires Electricity Provider TXNM Energy for $11.5 BillionAPPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE SETEX AREA RELIABILITY PROJECT IN JASPER, MONTGOMERY, NEWTON, POLK, SAN JACINTO, TRINITY, TYLER, AND WALKER COUNTIES - (179 filings)
APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (128 filings)
CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (122 filings)
BROKER REGISTRATIONS - (90 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR APPROVAL OF ITS 2026-2028 TRANSMISSION AND DISTRIBUTION SYSTEM RESILIENCY PLAN - (70 filings)
CY 2024 ANNUAL POWER LINE INSPECTION & SAFETY REPORT IN PURSUANT TO 16 TAC § 25.97(F) - (55 filings)
PROJECT TO SUBMIT EMERGENCY OPERATIONS PLANS AND RELATED DOCUMENTS UNDER 16 TAC § 25.53 - (53 filings)