PUCT approves plan for the first extra high voltage transmission lines in ERCOT region
Odessa American | Source: Odessa American | Posted 04/25/2025

AUSTIN In a landmark decision, the Public Utility Commission of Texas (PUCT) on Thursday approved a plan to build the Electric Reliability Council of Texas (ERCOT) region’s first extra high voltage transmission lines to meet the Permian Basin’s rapidly growing power needs.
AI generated summary
The Public Utility Commission of Texas (PUCT) has approved a significant plan to construct the first extra high voltage transmission lines in the Electric Reliability Council of Texas (ERCOT) region, aimed at addressing the increasing power demands of the Permian Basin. PUCT Chairman Thomas Gleeson emphasized the commitment to building a reliable ERCOT grid that minimizes disruption to landowners and natural habitats by utilizing fewer, more efficient lines that can carry greater power loads. The approval follows the enactment of House Bill 5066, which mandates an electric reliability plan to support the expansion of Texas' oil and gas industry and the electricity needs of West Texas communities.
This reliability plan represents the initial phase of a broader legislative effort to assess and enhance transmission and distribution systems across the ERCOT grid. Following a thorough analysis of costs and project timelines, the PUCT determined that while the extra high voltage option may incur a 22% higher initial cost compared to standard lines, it offers substantial long-term benefits. These include increased capacity to meet future demand, reduced congestion on existing lines, and potential cost savings by delaying the need for additional infrastructure as Texas continues to grow.
Link to Original Article
Please find the link to the full article below. (Please note that content provider might require a paid subscription)06/25 - 9:30 AM
ERCOT - SSWG Intro to MOD Training - Webex Only06/25 - 9:30 AM
ERCOT - RMTTF Meeting06/26 - 9:30 AM
ERCOT - Dispatchable Reliability Reserve Service (DRRS) Workshop V06/26 - 9:30 AM
06/24/2025
06/23/2025 Board of Directors Meeting06/24/2025
Gov. Greg Abbott Signs SB 6 To Improve Texas Grid Reliability06/24/2025
Texas Legislature Tilts Against Windmills: Is This the End of Wind Energy on the Texas Coast?06/24/2025
ERCOT CEO on summer preps, artificial intelligence stressing grid | Texas: The Issue Is06/24/2025
NERC report says BESS in ERCOT can improve primary frequency responseAPPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (150 filings)
BROKER REGISTRATIONS - (79 filings)
PROJECT TO SUBMIT EMERGENCY OPERATIONS PLANS AND RELATED DOCUMENTS UNDER 16 TAC § 25.53 - (47 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR DETERMINATION OF SYSTEM RESTORATION COSTS - (44 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (41 filings)
CY 2025 ELECTRIC UTILITY TRANSMISSION CONSTRUCTION REPORTS UNDER 16 TAC § 25.83 - (33 filings)
INFORMATIONAL FILING OF ERCOT INTERCONNECTION AGREEMENTS PURSUANT TO SUBST. R. §25.195(e) - (32 filings)