Meeting Summary - 04/18/2025 IBRWG Meeting
Grid Monitor AI | Posted 04/18/2025

▶️1 - Antitrust Admonition
▶️2 - NOGRR245 IBR Capability Maximization – Lessons Learned
Elevate_NOGRR245_Lessons_Learned-ERCOT_IBRWG_April_2025.pdf
- Elevate Energy Consulting and GridStrong teams involved in NOGRR245 exercises to improve Inverter-Based Resource (IBR) capabilities.
- Goals include reducing risks and improving IBR ride-through capability.
- Experience with over 100 units; lessons are shared anonymously.
- Explained the NOGRR245 process and its frequency ride-through requirements.
- Provided examples of IBR capability assessments and adjustments.
- Success of NOGRR245 in maximizing IBR performance and reliability.
- Maximization involves configuring IBR plant protections within equipment ratings to maximize ride-through capability.
- Coordination and optimization of protections are necessary without exceeding equipment ratings.
- OEM settings, ride-through curves, and protection coordination play a role in this process.
Challenges Identified
- Varied interpretations of 'maximization' without standard guidelines.
- Inconsistent settings and documentation from OEMs and across different models.
- Difficulties in aligning commissioning practices for new assets with maximization goals.
Recommendations
- Develop a standardized framework for IBR parameter settings accessible to stakeholders.
- Use of standardized data formats (IBR file) to ensure consistency and streamline RFI processes.
- Establish collaborations to address data access and settings at an industry level.
- Questions about protection settings and their impacts on inverters.
▶️3 - NOGRR245 IBR Capability Maximization – Lessons Learned (Zero Emission Grid) Mike Tabrizi, Zero Emission Grid
NOGRR-245-RFI-ZeroEmissionGrid-April-18-2025.pdf
- Acknowledged agreement with some presentation points; ZEG’s experience categorized into older plants with outdated inverters and OEMs, affecting plan verification and PGRR109 requirements.
- Newer projects experienced smoother processes due to better organization and verification compliance.
- Emphasized the importance of engineering assessment over purely numerical or document-based approaches to determine maximization capabilities.
- Sophisticated entities avoid overcommitting to RFI without sufficient engineering analysis, planned for full assessment by December 2025.
- Discussed various requirements (FRT, IEEE, VRT) based on resource entities' type, SGIA execution, and GIM execution post August 1st, 2024.
- Highlighted the necessity for extensive internal analysis of inverter capabilities relative to plant-level operations.
- Encouraged utilizing detailed PSCAD simulations for a realistic assessment of maximization capabilities.
- Outlined challenges in translating inverter specs to plant capability due to data gaps and overwhelming OEM data.
- Raised questions regarding ERCOT's DocuSign review process, the binding nature of submissions, potential for extensions, post-submission steps, and other areas needing clarity.
- Stressed the need for holistic capability assessments while avoiding reliance solely on broader spec values.
▶️4 - Comparison of NERC PRC-029, IEEE2800, NOGRR255
IBRWG-PRC-028-IEEE2800-and-NOGRR255-April-18-2025.pdf
- NERC’s PRC-028 standard was approved in February 2024 and takes effect July 1, 2025.
- The standard aims to improve disturbance data reporting from inverter-based resources (IBRs), driven by recent disturbances and reliability concerns.
- PRC-028 applies to both new and existing IBRs.
- In contrast, IEEE 2800 only applies to new units, and NOGRR255 (ERCOT rule) applies to both but with different levels of rigor.
- One key difference: PRC-028 drops the requirement for feeder-end fault recording, which NOGRR255 retains (at least SOE data for the last 10% of IBRs per feeder).
- Data requirements across standards include fault recording, SOE (Sequence of Events), and DDR (Dynamic Disturbance Recording).
- NOGRR255 adds monitoring of specific control commands and mode values, which aren’t required by PRC-028 or IEEE 2800.
- Presented details of differences for sampling rates, DDR output rates, time synchronization requirements, data retention and reporting timelines, and the restoration of failed equipment.
- Overall, NOGRR255 is stricter than PRC-028 in most technical areas, though PRC-028 has tighter deadlines and more rigid completeness expectations.
▶️5 - Other NERC Updates
- FERC directed NERC to develop standards for integrating IBRs
- PRC-028 and PRC-030 have been approved; PRC-029 is still under FERC review.
- PRC-029 received 23 comments, mostly about exemptions.
- Milestone Three includes three major projects on modeling and validation.
- Project 2020-06 defines terms like "validation" vs. "verification."
- Project 2021-01 focuses on MOD-033: validating models using system events.
- Project 2022-02 updates MOD-032, IRO-010, and TOP-003 for IBR data needs.
- Initial balloting opens this month; feedback is encouraged even if ballots fail.
- Technical conference scheduled for June (hybrid format).
- All Milestone Three deliverables due to FERC by November 2025.
- NERC issued a public report on IBR model deficiencies (April 1).
- Over 50% of IBR models do not match actual capabilities.
- Common issues: ride-through accuracy, limited VAR support (triangle limit).
- Texas data quality is slightly better than national average.
- New Level 3 Alert expected this summer with required data submissions.
- NERC plans to register Category 2 IBRs (>20 MVA, ≥60 kV) under a new “GO-IBR” category.
- No formal exemption process for PRC-029 yet; could model after CIP exceptions.
▶️6 - Other Industry Updates
ERCOT_IBRWG_Industry_Updates_041825_v1.pdf
- Spring technical workshop featured topics important to IBRWG, including sessions on oscillations and stability, grid forming inverters, and North Corridor 901 milestone three.
- Ontario IESO has included a requirement for all battery energy resources to have grid forming capability in their connection assessment application, aiming to future-proof the system.
- EPRI study in South Texas highlighted stability benefits of grid forming batteries and the importance of strategic placement for optimal effectiveness. This may involve case-specific tuning.
- Examples were provided of grid forming applications next to data centers and in the Chilean system, demonstrating benefits for voltage and frequency control, inertia, and system stability.
- Global tracking of interconnection requirements and specifications for grid forming is ongoing, including recent updates like FinGrid's publication.
- Discussion on i2X first, a DOE funded project addressing long interconnection queue waits and standards for inverter-based resources, focusing on improving interconnection reliability.
- Highlights from the ECIC technical workshop included discussions on conformity assessment, model validation efforts, periodic testing, and standards comparison.
- Upcoming i2X first meeting on April 29 will focus on voltage support, including discussions on VARs at night, voltage control, and reactive power requirements.
- Survey launched for feedback on i2X first meetings to improve the next round focusing on the adoption of IEEE 2800 and grid forming specifications, expected to start in May.
▶️7 - Other Business
- Participants were invited to bring up any additional items.
- Link was shared in the chat for signing up for the April first meeting.
- The shared link also contains recordings and summaries of previous events.
- No further questions were raised.
- Meeting concluded with thanks and a note to see attendees in May.
04/21 - 9:30 AM
LEGE - Senate Business & Commerce04/22 - 8:00 AM
ERCOT - Texas SET Meeting - Webex Only04/22 - 9:30 AM
ERCOT - RTCBTF Meeting04/22 - 9:30 AM
04/19/2025
Does the Texas Legislature Still Believe in Market Competition?04/19/2025
CPS Energy boosts wind power as part of plan to replace its aging plants04/19/2025
Data Centers’ Reliability Impacts Examined at FERC Meeting04/18/2025
Meeting Summary - 04/17/2025 Resource Entity and TSP Summer Weather Preparedness Workshop04/18/2025
Meeting Summary - 04/18/2025 IBRWG MeetingAPPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE SETEX AREA RELIABILITY PROJECT IN JASPER, MONTGOMERY, NEWTON, POLK, SAN JACINTO, TRINITY, TYLER, AND WALKER COUNTIES - (352 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR APPROVAL OF ITS 2026-2028 TRANSMISSION AND DISTRIBUTION SYSTEM RESILIENCY PLAN - (84 filings)
CY 2024 ANNUAL POWER LINE INSPECTION & SAFETY REPORT IN PURSUANT TO 16 TAC § 25.97(F) - (80 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY TO CONSTRUCT A PORTFOLIO OF DISPATCHABLE GENERATION RESOURCES - (68 filings)
BROKER REGISTRATIONS - (67 filings)
APPLICATION OF CROSS TEXAS TRANSMISSION, LLC FOR AUTHORITY TO CHANGE RATES AND TARIFFS - (59 filings)
APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (56 filings)