ERCOT calls new demand forecast a 'sanity check' amid Texas data center boom
Sara DiNatale | Source: San Antonio Express News | Posted 04/11/2025

The Texas grid boss unveiled what he called a “sanity check” demand forecast this week to assuage lawmakers’ fears that Texas power use would skyrocket past 200 gigawatts in less than five years.
AI generated summary
The Electric Reliability Council of Texas (ERCOT) recently presented a revised demand forecast, which it termed a 'sanity check' to address concerns from lawmakers about the potential surge in power usage due to the rapid growth of data centers in the state. ERCOT President and CEO Pablo Vegas indicated that while the adjusted forecast still predicts a significant increase of approximately 75% in demand, it provides a more realistic outlook compared to previous estimates that suggested demand could exceed 200 gigawatts by 2030. The new forecast estimates a peak demand of 148 gigawatts by 2030, taking into account the actual number of data centers that have materialized versus those that are merely speculative.
Despite this adjustment, skepticism remains among some lawmakers regarding ERCOT's methodology, particularly concerning the reliability of historical data given the recent influx of data centers. The forecast is based on a combination of signed contracts and letters of intent from transmission providers, but critics argue that many proposed projects may never come to fruition. As Texas aims to support the data center industry, ERCOT is tasked with ensuring that the necessary infrastructure is in place to meet future demand while avoiding potential grid overloads. Lawmakers are exploring legislative measures to enhance demand flexibility among data centers and improve the accuracy of future forecasts.
Link to Original Article
Please find the link to the full article below. (Please note that content provider might require a paid subscription)
Source Link: https://www.expressnews.com/business/article/ercot-demand-forecast-data-centers-texas-20267820.php
09/29 - 10:00 AM
PUCT - PUCT Meeting10/02 - 9:30 AM
ERCOT - ROS Meeting10/02 - 9:30 AM
ERCOT - CIPWG Meeting - Webex Only10/03 - 9:00 AM
09/27/2025
Microsoft among members of Schneider Electric-led US resilient community energy initiative09/27/2025
Climate Tech Atlas Could Unlock Net Zero Breakthroughs09/27/2025
Is nuclear fusion for real this time? These utilities think so.09/26/2025
09/25/2025 PLWG Meeting09/26/2025
Data centers are thirsty for Texas’ water, but state planners don’t know how much they will needAPPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (96 filings)
PROJECT TO DEVELOP COA AND SPCOA STATEWIDE AVERAGE SWITCHED ACCESS RATES FOR NOVEMBER 2025 PUBLICATION UNDER PURA § 52.155 AND 16 TAC § 26.223 - (91 filings)
BROKER REGISTRATIONS - (73 filings)
APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE DIVISION 138-KV TRANSMISSION LINE IN TARRANT AND DALLAS COUNTIES - (52 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE SETEX AREA RELIABILITY PROJECT IN JASPER, MONTGOMERY, NEWTON, POLK, SAN JACINTO, TRINITY, TYLER, AND WALKER COUNTIES - (35 filings)
APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (35 filings)
RULEMAKING TO IMPLEMENT FIRMING RELIABILITY REQUIREMENTS FOR ELECTRIC GENERATING FACILITIES IN THE ERCOT REGION UNDER PURA §39.1592 - (32 filings)