Meeting Summary - 10/16/24 RPG Meeting
Grid Monitor AI | Posted 10/17/2024
1 - Antitrust Admonition
2 - Miscellaneous Updates - ERCOT
3 - EIR Status Update – Delaware Basin Stages 3 and 4 Project - ERCOT - Tanzila Ahmed
EIR - Oncor - Delaware Basin Stages 3 and 4 Project - Status Update - RPG October 2024
- Tanzila Ahmed presented the EIR status update for the Oncor Delaware Basin stages 3 and 4 project.
- The project is a Tier 1 project with an estimated cost of $202.2 million.
- Estimated in-service date is 6/1/2027, and is subject to change..
- Project need and solution were identified in the 2019 Delaware Basin Load Integration project Load interconnection study.
- Steady state power flow analysis was conducted to identify and evaluate project options.
- The project resolved 20 pre-project voltage violations and four power flow issues.
- Congestion analysis showed no new congestion for the preferred option.
- ERCOT recommends Oncor's proposed option.
- Construction includes a new 345-kV double circuit line and a 138-kV line.
- Final EIR report will be posted in November 2024.
- Recommendations for TAC and R&M meetings are planned for November and December 2024, respectively.
- No questions were posed following the presentation.
4 - EIR Status Update – Venus Switch to Sam Switch 345-kV Line Project - ERCOT - Sarah Gunasekera
EIR ONCOR Venus Switch to Sam Switch Project OCT Update
- The Venus Switch to Sam Switch 345-kV line project is a tier one project submitted to RPG in June; estimated cost is $118.9 million, and completion is expected by May 2026.
- The project addresses post contingency thermal overloads and does not require a CCN.
- ERCOT is conducting an independent review of the project, specifically in Hill and Ellis counties, focusing on the Venus switch to Sam Switch double circuit 345-kV line.
- Transmission updates have been made in terms of approved and studied RPG projects with in-service dates prior to May 2026.
- Generation and confirmed loads in the north and north central weather zones have been updated.
- Updated preliminary reliability analysis shows thermal overloads in N-1, G-1, and X-1 cases.
- Three project options have been proposed, all solving thermal violations with no additional thermal or voltage violations under various conditions.
- Further assessments include long-term load serving capability, cost and feasibility assessments, generation addition and load scaling sensitivity analyses, subsynchronous resonance assessment, and congestion analysis.
- Updates will be provided at future RPG meetings and the final project recommendation is expected in quarter four of this year.
5 - EIR Status Update – Wilmer 345/138-kV Switch Project - ERCOT - Ying Li
EIR - Oncor - Wilmer 345138-kV Switch Project - Status Update - RPG Oct2024
- ERCOT's Ying Li presented an independent review status update for the Oncor Wilmer switch project.
- The Wilmer project is a tier-one project in Dallas County with a cost estimate of $158 million, requiring a CCN with an estimated in service date of May 26.
- The project aims to address summer overloads at the Wilmer substation, driven by a large new contracted load.
- ERCOT and Oncor provided a project overview and study scope at the September RPG meeting.
- ERCOT conducted a reliability need analysis based on the final 2023 RTP 2028 North/North-Central Summer peak case.
- Results showed unsolvable contingencies under certain conditions and various thermal and voltage violations.
- Three options were evaluated to address reliability needs:
- Option 1 (Oncor Proposed): Expanding Wilmer substation, installing transformers, capacitors, double circuits, and upgrades, which resolved all violations.
- Option 2: Looping the Watermill to Tricorner circuit at Wilmer, left one overload unresolved.
- Option 3: Looping the Watermill to West Levee line at Wilmer, also left one overload unresolved.
- Additional evaluations and analysis are ongoing, with a final recommendation expected by December.
- No questions or comments followed the presentation.
6 - Hartring to Upland 138-kV Line and Benedum Autotransformer Addition Project Overview - Oncor
24RPG024 Oncor and LCRATSC RPG Overview for ERCOT 10-16-2024
- Oncor and LCRA are collaborating on an RPG project to address load growth and voltage issues in Oncor’s southern Stanton Loop area.
- Oncor's project includes a 9-mile, 138-kV double circuit line and reconfiguration of the Ringo station, with a cost of $25 million.
- The project area is experiencing thermal and voltage violations due to significant load growth.
- LCRA plans to install a new 345-kV source and autotransformers, with a project cost of $69 million.
- The LCRA portion will strengthen the 138-kV network and increase resiliency and voltage support.
- The total estimated project cost is $94 million, categorized as a tier two project with an expected review completion by Q1 2025.
- Construction is anticipated to start in 2025, with Oncor's portion taking 2-3 years.
- The project benefits include mitigating voltage and thermal violations and supporting long-term load requirements.
- A key question addressed was confirmation of the Benedum station's location on the LCRA 345-kV portion.
- Oncor is considering future upgrades, including possible additional 345-kV installations at Catclaw.
7 - ERCOT Independent Review Scope Hartring to Upland 138-kV Line and Benedum Autotransformer Addition Project - ERCOT - Tanzila Ahmed
- Reviewed a map showing voltage and thermal violations in specified areas.
- Discussed projects by Oncor and LCRA involving new circuits and transformer additions.
- Study area focuses on the far west weather zone, with monitoring of nearby counties.
- Study will use the final 2023 RTP 2026 summer peak load case for adjustments.
- Projects in-service before summer 2025 will be included, while unapproved projects are excluded.
- New generation resources meeting certain conditions are added to the study base case.
- Compliance with 2024 RTP methodology for generation dispatch.
- Load levels maintained per 2023 RTP; oil, gas, and new confirmed loads will be updated.
- Contingency planning includes analysis of specific power units and transformers.
- Evaluation of alternatives for project needs and reliability requirements.
- Planned maintenance outages and cost estimates will be reviewed.
- Potential congestion analysis for proposed upgrades.
- Status updates to be provided at future RPG meetings.
- Final recommendations are scheduled for completion in early 2025.
8 - Tredway 138-kV Switch and Expanse to Tredway 138-kV 2nd Circuit Project Overview - Oncor - Eduardo Camilla
- Eduardo Camilla introduced the Tredway 138 kV switch project for Oncor to address load growth in the Midland basin.
- The project aims to mitigate post contingency low voltage and thermal overload issues within the Oncor system.
- Oncor proposed a RPG project entailing 28.8 miles of 138 kV transmission line rebuild with double circuit cable structures.
- The project includes 3.6 miles of new 138 kV lines and re-terminating existing lines at Vealmoor and Tredway.
- A new Tredway 138-kV switching station will be built, along with capacitor banks expansions, totaling up to $119.03 million.
- The project spans Martin, Howard, and Borden counties.
- Construction is expected to start in 2025 and complete by 2026, with no CCN applications anticipated.
- There was a discussion regarding whether the project was included in the Permian Basin reliability plan.
- Mark inquired if the project was part of the Permian Basin plan, and it was clarified that these are additional projects.
- Robert and Oncor agree on providing clarity regarding project inclusion in future presentations.
- Sarah from ERCOT was invited to discuss the scope presentation following Eduardo’s overview.
9 - ERCOT Independent Review Scope Tredway 138-kV Switch and Expanse to Tredway 138-kV 2nd Circuit Project - ERCOT - Sarah Gunasekera
- Presentation on the Oncor Tredway 138-kV switch and expansion to the Tredway 138-kV second circuit project.
- Project addresses post-contingency thermal overloads and voltage violations on the 138-kV line between Vealmoor to Buzzard Draw.
- Project involves expanding the 138-kV line to a double circuit and adding the Tredway substation near Vealmoor.
- Study focuses on west and far west weather zones, specifically Martin, Howard, and Borden counties.
- 2023 RTP 2026 summer peak west Far West case used for analysis.
- New generations meeting planning guide section 6.9(1) conditions and approved loads in the study area added to the case.
- Focused on criteria such as N-1, G-1, and X-1 one for the project.
- Study procedures include need analysis, ERCOT alternatives, maintenance outage planning, load serving, generation addition, load scaling, resonance assessment, and congestion analysis.
- Future updates and final recommendations scheduled for quarter one of 2025.
- No comments or questions from the audience after the presentation.
10 - 2024 Long-Term System Assessment LTSA Transmission Expansion Analysis Update for Current Trends - ERCOT - Pengwei Du
2024 Long-Term System Assessment (LTSA) Current Trends_Transmission_v4.1
- Discussed the 2024 LTSA Transmission Expansion Analysis using current trends.
- Explained the LTSA study framework, starting with scenario development followed by generation capacity expansion analysis using a zonal model.
- The first iteration does not consider transmission limitations; the second iteration uses a three-zone model focusing on West Texas airport and panhandle interface limits.
- Results indicate a need for 88 gigawatts of new resources by 2039, broken down by types such as storage, solar, wind, etc.
- Analysis includes mapping new resources to nodal models and assessing transmission needs and congestion costs.
- Congestion costs were estimated for 2034 ($2.2 billion) and 2039 ($3.2 billion), with significant costs from West Texas airport interface and other areas.
- Next steps for ERCOT include evaluating transmission projects to improve efficiency and address congestion.
- Engaged in Q&A discussing load growth, economic model assumptions, feasibility of generation sites, and possible future inclusions of load projections.
- Suggestions included providing more comprehensive tables summarizing generation and load, historical context of LTSA, and considering factors like SMRs and geographic feasibility in future analyses.
11 - ERCOT Extra-High Voltage Infrastructure Update - ERCOT
ERCOT EHV Infrastructure Initiative Update October 2024
- ERCOT is discussing their Extra-High Voltage (EHV) infrastructure plans, focusing on the 765 kV plan divided into two phases: initial build (Phase 1) and future expansion (Phase 2) beyond 2030.
- The purpose is to optimize the plan for 2030 load projections by comparing standard RPG assessments with EHV strategies.
- Two proposals for the 765 kV plan are being developed, which include cost, system loss comparisons, and analysis of system stability and congestion by mid-January 2025.
- An update could be expected in November, with more finalized plans by December. Workshop facilitation is also planned for further stakeholder discussions.
- Questions arise around compliance requirements for both 345 and 765 kV studies, cautious about using 'limited' in describing the analysis scope.
- Clarifications were made about capital cost considerations and analysis depth for both the 345 kV and 765 kV infrastructure, conveying that detailed feasibility and cost studies will be forthcoming.
- Clarification on shunt reactors needed for 765 kV plan, indicating a baseline assumption of necessities despite not completing all feasibility analyses.
- Discussions around handling redundancy criteria and maintenance for 765 kV alongside the need for making generation assumptions were noted.
- Feedback processes and internal ERCOT discussions will inform the decisions on regional planning group submissions as well as for evaluating 345 vs. 765 kV plans.
- Highlighted bandwidth and timing constraints in conducting comprehensive feasibility analyses, particularly concerning construction feasibilities for TSP’s.
12 - Long-Term Load Forecast update - ERCOT - Sam Morris
Long Term Pre-Liminary Schedule_RPG
- ERCOT plans to modify the schedule of the long-term load forecast updates. This is due to various contracts, officer letters and study loads.
- The updated forecast will include electric vehicles, photovoltaic, large flexible load forecasts, and will be presented mainly for the SAWG and CDR.
- ERCOT will conduct a survey asking participants for additional input, aimed for a late March or early April update.
- There is a strong focus on improving transparency and accuracy, with a suggestion to provide updated load type charts on a quarterly basis.
- ERCOT is working on consolidating data requests into one request to minimize burden on participants, possibly developing a portal for information transfer.
- Clarification was made that the term 'large flexible load forecast' includes crypto data centers, not AI data centers.
- Request for a comprehensive process for collecting officer letters with appropriate market notices to avoid miscommunication seen previously.
- The potential for large loads to have on-site generation is being considered in upcoming surveys.
- The percentage curtailment for large flexible loads might increase, based on observed behaviors during peak times.
- ERCOT plans to release the next survey around January 2 to incorporate data regarding co-located generation.
13 - Adjourn - ERCOT
04/24 - 9:30 AM
LEGE - Senate Business & Commerce04/24 - 8:00 AM
LEGE - House 89th Legislative Session04/24 - 10:00 AM
ERCOT - TWG Meeting - Webex Only04/24 - 2:00 PM
04/24/2025
Meeting Summary - 04/24/2025 Open Meeting04/24/2025
Meeting Summary - 04/23/2025 Market Design Framework Workshop04/24/2025
Cool solar tech: Who’s ready for AI-powered construction robots and quantum dots?04/24/2025
U.S. solar capacity expected to triple in next 10 years04/24/2025
XPrize in Carbon Removal Goes to Enhanced Rock WeatheringAPPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE SETEX AREA RELIABILITY PROJECT IN JASPER, MONTGOMERY, NEWTON, POLK, SAN JACINTO, TRINITY, TYLER, AND WALKER COUNTIES - (283 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR APPROVAL OF ITS 2026-2028 TRANSMISSION AND DISTRIBUTION SYSTEM RESILIENCY PLAN - (85 filings)
CY 2024 ANNUAL POWER LINE INSPECTION & SAFETY REPORT IN PURSUANT TO 16 TAC § 25.97(F) - (79 filings)
APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (76 filings)
BROKER REGISTRATIONS - (67 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY TO CONSTRUCT A PORTFOLIO OF DISPATCHABLE GENERATION RESOURCES - (59 filings)
APPLICATION OF CROSS TEXAS TRANSMISSION, LLC FOR AUTHORITY TO CHANGE RATES AND TARIFFS - (55 filings)