Meeting Summary - 09/25/24 RPG Meeting
Grid Monitor AI | Posted 09/27/2024

1 - Antitrust Admonition
2 - Miscellaneous Updates - ERCOT
- Caleb Holland is leaving the regional planning group.
- This will be Caleb's last presentation as a member of the regional planning group.
- Caleb received thanks for his years of hard work and dedication.
- Caleb's final update involves the Brownsville project.
3 - EIR Status Update – Brownsville Area Improvements Transmission Project - ERCOT - Caleb Holland
EIR - AEPSC Brownsville Area Improvement_Status Update_Sept 2024
Overview: Final status update on the AEP Brownsville Improvements transmission project.
- Project Recap: Submit by AEP in March 2024, estimated cost $388M, service date May 2027.
- Project Scope: Addressed thermal overloads and voltage violations in Brownsville area with new load additions.
- Status: Provided regular updates, project under ERCOT independent review.
- Geographical Focus: South weather zone, particularly Brownsville area in Cameron County.
- Shortlisted Options and Details: Explained technical specs and differences of options 2a, 5a, 7, and 8.
- Evaluation Results: Detailed the voltage violations and thermal overloads for various options.
- Preferred Option Selection: ERCOT selected option 2a - least cost, met all criteria, required less CCN mileage, improves operational flexibility.
- Sensitivity Analyses: Generation addition and load scaling sensitivities showed no material impact on project.
- Congestion Analysis: Identified one newly congested line, not recommended for upgrade.
- Next Steps: EIR report posting, TAC recommendation in October, ERCOT board endorsement in December.
- Q&A Highlights: Discussion on load coverage, decision making between options, concerns about confirmed vs. officer letter loads.
- Additional Comments: Need for external discussions between AEP and Sharylandto resolve differing views surrounding project.
4 - EIR Status Update – Rand Area Loop Project - ERCOT
Rand_Area_Loop_Project_RPG_09252024.pdf
- Presenter: Abhishek Penti
- Rayburn Electric Cooperative (REC) submitted the Rand Area Loop project for RPG review in May 2024, a tier two project estimated at $32.2 million requiring a CCN.
- Estimated in-service date is April 2027.
- Purpose: Limit radial load to less than 20 MW and provide “looped service” to REC Rand substation.
- Project is currently under ERCOT independent review.
- ERCOT conducted a steady-state load flow analysis based on TPL-001-5.1 and planning criteria with no voltage, thermal, or unsolved power flow violations found.
- Seven options evaluated with three proposed by REC and four by ERCOT.
- Options 1 and 2 had thermal violations for N-1 contingency scenarios.
- Options 3, 4, 4a, 5, and 6 selected for further evaluation.
- Option 5 deemed infeasible due to Explorer switching station constraints; remaining options require a CCN and are feasible.
- Plant maintenance outage evaluation showed no voltage violations, thermal overloads, or unsolved power flow violations for shortlisted options.
- Long-term load serving capability analysis performed; Options 3, 4, and 4a performed similarly, while Option 6 had less capability.
- All four shortlisted options (3, 4, 4a, 6) meet reliability criteria, REC planning criteria, and improve long-term load serving capability.
- Option 3 is the preferred option: least expensive, fully addresses REC planning criteria, no reliability issues, improves operational flexibility, and enhances long-term load serving capability.
- Congestion analysis (using 2023 RTP 2028 economic case) showed no new congestion within the study area.
- Option 3 details:
- Estimated cost $32.2 million
- Service date April 2027
- Involves new 138-kV switch yard between Explorer and Glen Pine 138-kV line with a new 138-kV line from Rand to the new switchyard, approximately 12.35 miles.
- ERCOT protocol section 3.11..4.9(4) endorses this project to meet REC planning criteria.
- EIR will be posted to MIS in October.
- No audience questions; next presentation: Oncor Delaware basin stages 3 and 4, under ERCOT independent review.
5 - EIR Status Update – Delaware Basin Stages 3 and 4 Project - ERCOT - Tanzila Ahmed
Oncor_Delaware_Basin_Stages3and4_Project_Status_Update_RPG_09252024_18l1p7kw06lrb.pdf
- Project submitted by ERCOT in March 2024 with an estimated cost of $202.2 million.
- Estimated in-service date is summer 2027.
- Project aims to address reliability issues in Delaware Basin area due to significant load growth primarily for oil and gas.
- Previous studies: 2019 Delaware Basin Load Integration and 2024 Permian Basin Reliability Plan.
- Stage 1 upgrade completed in 2023, Stage 2 upgrade expected in 2026, Stage 5 upgrade under review.
- Stage 3 involves a new 345-kV substation, double circuit 345-kV line from Riverton to Drill Hole, and transformer upgrades.
- Stage 4 involves a double circuit 345-kV line from Sand Lake to Riverton.
- Reliability analysis includes sensitivity analysis and planned maintenance outage evaluation.
- Total of 20 voltage violations including 2 generation violations and 2 transformer violations, and 4 unsolved power flow issues identified. All solved by the proposed project.
- Upcoming tasks: conducting congestion analysis, updating cost estimates, and providing further status updates.
6 - EIR Status Update – Venus Switch to Sam Switch 345-kV Line Project - ERCOT
ONCOR_Venus_Switch_to_Sam_Switch_Project_Update_09252024.pdf
Discussions:
Presenter: Sarah Gunasekera
- Oncor submitted the project RFP in June, estimated cost is $118.9 million and will not require a CCN.
- Project to be completed by May 2026.
- Addresses post contingency thermal overloads on the Venus switch to Sam switch double circuit 345-kV line.
- Project is currently under ERCOT independent review.
Study Assumptions
Using 2023 RTP for 2026 summer case, adding 730 confirmed load, maintaining 2023 RTP reserve levels.
Preliminary Results
- Three voltage violations under N-1 conditions, seen also under G-1 and X-1.
- Four thermal overloads under P1 and one under P7 conditions.
Options
- Option 1: Oncor proposed project, upgrading various 345-kV lines totaling about 76 miles.
- Option 2: Includes upgrades in Option 1 plus Venus switch to Navarro 345-kV line upgrade of 33.2 miles.
Preliminary Results for Options
- No thermal or voltage violations in N-1 study for Options 1 and 2.
- Thermal and voltage violations observed under G-1 and X-1 conditions.
- Decrease in thermal violations seen, especially in Option 2.
Next Steps
- Study additional project alternatives to satisfy ERCOT reliability criteria.
- Perform evaluations on plan maintenance outage, long term load serving capability, generation addition and load scaling sensitivity, subsynchronous resonance assessment, and congestion analysis.
Timeline: Final recommendation expected in Q4 of this year.
Q&A:
- Questioner: Sunil Dhakal, Lone Star Transmission
- Question: Are there plans to look into 345-kV in the area?
- Response: Potentially, evaluation ongoing.
- Questioner: Harsh, Oncor
- Question: Clarification on treating 345-kV overloads and 69-kV voltage issues separately.
- Response: Evaluating solutions for Waxahachie area, particularly Wilmer project, considering additional generation resources and load in northern Dallas. Conclusions not yet solidified.
7 - ERCOT Independent Review Scope: Connell 345/138-kV Switch and Connell to Rockhound 345-kV Double-Circuit Line Project
Oncor_Connell_to_Rockhound_RPG_Project_SCOPE_09252024_RPG_1.pdf
- Ben was unavailable to present; Robert Golan took over.
- Project submitted by Oncor in June 2024.
- Tier one project costing $110.62 million, requiring a Certificate of Convenience and Necessity (CCN).
- Estimated in-service date: December 2026.
- Addresses low voltages and thermal overloads expected by summer 2025 due to significant load growth in the western portion of Texas, primarily from the oil and gas industry.
- Project includes various constructions and installations:
- New Connell 345/138-kV switching station.
- Two new Connell to Rockhound 345-kV lines (13 miles).
- New circuitry and breakers at multiple existing switches.
- Reconfiguration of existing connections within the studied areas.
- Scope and study area: Western Texas counties focusing on Midland and Martin.
- Will follow NERC TPL-001-5.1 and ERCOT planning criteria.
- Timeline for final recommendation: Q4 of 2024, with status updates at future RPG meetings.
- No questions from the audience; the presentation moved to the next agenda item on the Forty 345/138-kV switch rebuild project.
8 - Forney 345/138-kV Switch Rebuild Project Overview - Oncor
Oncor_Forney345-138kV_Switch_Project_RPG_09252024.pdf
- Rebuild project is estimated to cost $103.5 million.
- The project addresses thermal violations, replaces aging infrastructure, and enhances system reliability.
- Existing switching station details: 345-kV double bus double breaker configuration, 138-kV single bus with 345/138-kV auto transformer rated at 750 MVA.
- New switch configuration will be in a breaker-and-a-half layout.
- Installation of a second 750 MVA auto transformer and a 110.4 MVAR capacitor bank at Forney was proposed.
- Main driver of the project is the thermal violations observed at the existing Forney auto transformer.
- Existing infrastructure at Forney was built in the 1960s and lacks modern microprocessor relays.
- Rebuild scope: 345-kV equipment rated at 5,000 AMP, 138-kV equipment rated at 3,200 AMP, new auto transformer rated at 750 MVA, and relocation of the Forney substation.
- Reactive support needs identified by real-time operational data showing low voltages in Dallas and Kaufman County.
- Capacitor banks proposed to address low voltage issues not captured by models but observed in real-time operations.
- Operational feedback prompted the reactive support installations to maintain system voltage around one per unit.
- No further questions from attendees after the presentation.
9 - ERCOT Independent Review Scope: Forney 345/138-kV Switch Rebuild Project - ERCOT
Oncor_Forney_345_138-kV_Switch_Rebuild_Project_RPG_09252024.pdf
- Presentation given by Abishek Penti for Oncor's NSW project.
- Project submitted to RPG in July 2024, estimated cost of $103.5 million.
- In-service date estimated to be December 1, 2025.
- Purpose: Address post-contingency thermal violations and replace aging infrastructure.
- Project includes installing multiple 345 kV and 138 kV breakers in a breaker and a half arrangement and adding an auto transformer.
- Switch rebuild aims to improve operational flexibility and system reliability in Dallas Fort Worth region.
- ERCOT independent review involves monitoring north and north central weather zones, focusing on Dallas and Kauffman counties.
- Base case to be updated using 2023 RTP for 2026 summer peak.
- Loads consistent with 2023 RTP methodology; newly approved loads added to the base case.
- Contingency analysis to follow specific ERCOT regulations and criteria, monitoring various parameters like thermal and voltage limits.
- Study procedure includes need analysis, project evaluation, sensitivity analysis, subsynchronous resonance (SSR) assessment, and congestion analysis.
- Status updates to be provided in future RPG meetings with a final recommendation by Q4 2024.
- No questions or comments from the attendees after the presentation.
10 - Wilmer 345/138-kV Switch Project Overview - Oncor
Oncor_Wilmer345-138kV_Switch_Project_RPG_09252024.pdf
- Oncor presented an overview of the Wilmer 345/130-kV switch project.
- The project aims to establish a 345/130-kV switch in Dallas County, referred to as Wilmer Switch.
- Projected cost: $158.2 million.
- Purpose: Address large load request of 756 MW at Wilmer 130-kV substation, preventing thermal violations and enhancing network reliability.
- Location selection criteria: Proximity to load request and economic viability.
- Project includes: Establishing a new 345/130-kV switch and two new transformers, terminating certain lines into Wilmer Switch, and rebuilding portions of the existing Watermill 345 kV line.
- Rebuild and convert existing 69 kV line from Wilmer to Ferris to 130 kV operation.
- Confusion addressed on how interconnection agreements are signed: Explained that agreements are contingent on approval and customers are informed of required upgrades. Load does not come online until 2026.
- End use classification of the load: Data center, non-crypto.
11 - ERCOT Independent Review Scope - Wilmer 345/138-kV Switch Project - ERCOT
Oncor_Wilmer_345138-kV_Switch_Project_Scope_RPG_09252024.pdf
- ERCOT independent review study scope for the Wilmer 345/138 kV switch project presented by Yin Li.
- Described overload issues in the Wilmer area due to new load, including Wilmer, Watermill, Seagoville, Forney, Kaufman, and the south area.
- Oncor's proposed solution: Wilmer 345/138 kV project with two transformers and transmission upgrades.
- Study assumptions, including region focus (North Central weather zone), use of 2033 RTP and 2028 thermal peak case for data.
- Transmission projects with in-service dates before summer 2028 and relevant additions and removals detailed in appendices A and B.
- Generation projects included based on August GIS report and adhering to 2023 RTP methodology.
- Load assumptions include an additional 756 MW new confirmed load at Wilmer.
- Contingency and criteria adherence, including techniques like need analysis, sensitivity analysis, SSR assessment, and congestion analysis.
- Timeline goal to complete the study by December.
- Question raised about performing dynamic stability studies for the large new load. Oncor confirmed no stability issues were found.
- Clarified that ERCOT relies on TSP's stability study results unless specific stability issues are identified.
- Confirmation that necessary stability studies were performed by Oncor, with a request to specify dynamic models used.
- Yang Zhang (WETT) highlighted the importance of naming and organizational clarity for meeting minutes.
- Further comment from another participant emphasized the need to reassess if the RPG study results match TSP studies, regarding the need for dynamic stability studies.
- Conclusion with an acknowledgment of no more questions, and the next item handed back to Oncor for the Delaware Basin stage five project overview.
12 - Delaware Basin Stage 5 Project Overview - Oncor
Delaware_Basin_Stage5_RPG_Overview_for_ERCOT_09252024.pdf
- ERCOT's 2019 Delaware Basin Load Integration Study identified 5 stages of transmission upgrades
- Stage 5 necessary when load exceeds 5,422 MW, anticipated by summer 2025
- Load levels based on SSWG cases from October 2023
- Oncor analysis found numerous contingencies causing low voltages and thermal violations
- Proposed upgrades include 220 miles of 345-kV double circuit line
- Project components: expanding 138 kV switchyard at Lamesa, new 138-69 kV switching station at Welch, rebuilding Clearfork 345 kV switch
- Estimated project cost: $744.6 million
- Project impacts eight counties: Andrews, Borden, Culberson, Dawson, Gaines, Loving, Reeves, Winkler
- Significant load growth attributed to oil and gas industry and inverter-based resources
- Expected to enhance reliability and import capability for West Texas
- Detailed scope of transmission upgrades outlined with specific line mileages and terminus points
- Project requires multiple CCN applications, construction from 2025 to December 2029 depending on various factors
- RPG submittal comment period ended May 28, ERCOT Independent review by November 22
- Following the overview, questions from Cyrus and Kevin addressed matters related to potential 765 kV line alternatives and reliability impacts
- Subsequent presentation for Delaware Basin Stage 5 project alternatives
13 - Delaware Basin Stage 5 Project Alternative Overview - WETT
WETT_DB5_Alternative_Overview_RPG.pdf
- Presentation by WETT on Delaware Basin Stage 5 project alternatives.
- Background: Need for system upgrades in the Delaware Basin to serve oil and gas loads identified in 2019. ERCOT 2023 RTP study confirmed this need.
- Oncor submitted its proposal in May; WETT submitted an alternative in June, with a final version in August.
- WETT's proposal is a Tier 1 project, with a portion to be in service by December 2028.
- Cost for WETT's portion: $305 million.
- WETT's proposal vs. Oncor's: Focus on using local 130 kV facilities to address load-serving needs while avoiding Lamesa area reliability issues.
- Comparison: WETT offers a potentially more cost-effective solution, with similar performance in power flow, stability, and short circuit analyses as Oncor's proposal.
- Conclusion: Both proposals solve reliability needs; WETT suggests ERCOT compare and review both to decide the best approach.
- No questions were raised after the presentation. The next session will be an independent review scope presentation by ERCOT.
14 - ERCOT Independent Review Scope - Delaware Basin Stage 5 Project - ERCOT
EIR - Oncor - Delaware Basin Stage 5 Project - Scope - RPG September 2024
- Tanzilla Ahmed presented the scope for the ERCOT independent review for the delay air Basin stage five project.
- ERCOT is conducting a single EIR review for both Delaware Basin Stage 5 alternatives.
- Study region: Far West Weather Zone (Andrews, Borden, Culberson, Dawson, Gaines, Loving, Reeves, and Winkler counties).
- Using 2023 final RTP case for 2029 summer transmission upgrades.
- Including all approved RPG projects and placeholders for Delaware Basin stages 3 and 5 based on previous presentations.
- Updated based on 2024 TPIT published in July.
- Generation analysis using 2024 GIS report and considering new generations with COD before December 2029.
- Consideration of recent retired and indefinitely modball units for status loads.
- Updating oil and gas loads based on 2024 SMP global forecast.
- Ensuring reserve maintenance with 2023 RTP criteria.
- Specific assessment of turning off all five Permian Basin generations and Odessa combined cycle train one for transformer.
- Focus on Riverton, San Lake, and Long Draw transformers.
- Reliability need analysis with contingencies and evaluation against NERC & ERCOT reliability requirements.
- Assessment of long-term load serving capability, congestion analysis, cost, and feasibility.
- Future status updates at RPG meetings and final recommendation tentatively by Q4 2024.
- Robert Golan clarified that the review primarily compares two options but may include upgrades identified during evaluation.
15 - 2024 RTP Economic Study Preliminary Results - ERCOT
2024_RTP_Economic_Study_Results_20240925_vs3opiy4w6hb.pdf
- Two base cases for study years 2026 and 2029 created.
- Full study results and report expected by year-end.
- Improvement in battery dispatch model with vendor LCG.
- Evaluation of transmission projects based on economic benefit and efficiency.
- Peak loads: 90,702 MW (2026) and 94,410 MW (2029).
- Energy production: Natural gas (44%-48%), wind & solar (~40%), nuclear and coal fill remaining demand.
- Significant wind and solar capacity modeled for both years, with increases expected by 2029.
- Total congestion cost: $1.1 billion (2026) and $928 million (2029).
- High congestion in areas including West Texas, Panhandle, Houston Interface, and Lubbock region.
- Various questions addressed regarding battery dispatch improvements, load growth impacts, congestion cost reductions, and economic project evaluations.
16 - ERCOT Extra-High Voltage Infrastructure Update - ERCOT
ERCOT_EHV_Infrastructure_Initiative_Update_09252024_RPG.pdf
Presenter Name: Jameson Hessler
- Overview of initial violations from this year's traditional RTP.
- Introduction and discussion of two-phase EHV plan: Phase One and Phase Two.
- Phase One includes 765kV lines based on Permian Basin study and Eastern Connection.
- Phase Two is a potential future expansion including panhandle and valley components.
- Challenges in quantifying EHV benefits in current RTP analysis.
- ERCOT's effort to incorporate feedback from TSPs and other stakeholders.
- Testing and analyzing EHV plan under 2030 RTP case.
- Coordination with PUC's timeline for the Permian Basin study and EHV project.
- Economic analysis considerations and qualitative benefits of 765kV lines.
- Need to quantify qualitative benefits such as increased transfer capability and reduced line losses.
- Clarifications on TSP involvement and the selection process for discussions.
- Plan to manage new and changing load requests in future RTP cases.
- Conversations and feedback sessions with TSPs regarding routing challenges.
- Final proposal and next steps towards a December 2024 conclusion.
- Further discussion with attendees regarding future studies and timing of EHV projects.
17 - 2024 RTP Sensitivity Study Assumptions - ERCOT
2024_RTP_Sensitivity_Assumptions_09252024_RPG_sndp5rkfazmq.pdf
- RTP sensitivity analysis required by NERC includes an off-peak condition and two system peak conditions.
- The 2024 RTP sensitivity will use the minimum load case for 2027, and peak load sensitivity for 2026 and 2029.
- All officer letter loads will be scaled to 50% of their full value while contract loads remain unchanged.
- Generation changes will focus on generation hubs being turned off; other generation assumptions remain unchanged.
- IA and FIS only generation remains, significant particularly in the 2029 case.
- Reduction in officer letter loads illustrated with specific columns providing total system load and contract load context.
- Q&A highlighted why 50% scaling for officer letter loads was chosen—there's no perfect number, it's a starting point for stakeholders.
- Intent is to provide a baseline for stakeholders to conduct their own sensitivity analysis and evaluations.
18 - 2024 Grid Reliability and Resiliency Assessment Assumptions Update - ERCOT
2024_Reliability_and_Resiliency_Assessment_Assumptions_09252024_RPG.pdf
- Introduction by Tyler Long from ERCOT on reliability and resiliency assessment assumptions.
- Study mandated by Senate Bill1281 and Texas Administrative Code 25. 101.
- Assessment of extreme weather scenarios: extreme winter weather and summer hurricane scenarios.
- Base case: final 2029 summer case, updated with new generation and approved RPG projects.
- Summer hurricane scenario: worst-case scenario with Houston landfall, Category 5, 160 mph winds, 22ft storm surge.
- Wind and solar dispatch based on 2024 RTP methodology.
- Extreme winter scenario: transformed load from summer to winter based on 2021 winter weather year.
- Winter peak forecast: initial 91 GW, final 105 GW after adjustments.
- Capacity loss due to extreme cold weather based on historical analysis of storms Uri, Elliott, and Heather.
- Battery dispatch: based on state of charge during top four load hours of coldest day plus two following days.
- Thermal generation loss capacity: average based on historical outages during top four peak load hours of storms Uri, Elliott, and Heather.
- Identified total thermal loss capacity: 9,400 MW (gas 7,000 MW, coal 2,000 MW).
- Study criteria: p0, p1, p2, and p7 contingencies to prevent cascading events and uncontrolled islanding.
- Final presentation conclusion with no additional questions or concerns raised.
19 - Adjourn - ERCOT
05/05 - 8:00 AM
LEGE - House State Affairs05/05 - 8:00 AM
LEGE - House 89th Legislative Session05/05 - 10:00 AM
ERCOT - WMWG Meeting - Webex Only05/05 - 9:30 AM
05/03/2025
ERCOT eyes late-July power emergency risk as demand soars05/03/2025
‘Sustainable AI’ requires close collaboration between data centers, grid stakeholders: Schneider Electric05/03/2025
Demand Growth and Carbon Targets Prompt New Interest in Nuclear05/02/2025
Meeting Summary - 05/02/2025 Residential Demand Response Workshop05/02/2025
Meeting Summary - 05/01/2025 RMTTF MeetingAPPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE SETEX AREA RELIABILITY PROJECT IN JASPER, MONTGOMERY, NEWTON, POLK, SAN JACINTO, TRINITY, TYLER, AND WALKER COUNTIES - (322 filings)
CY 2024 ANNUAL POWER LINE INSPECTION & SAFETY REPORT IN PURSUANT TO 16 TAC § 25.97(F) - (87 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR APPROVAL OF ITS 2026-2028 TRANSMISSION AND DISTRIBUTION SYSTEM RESILIENCY PLAN - (82 filings)
APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (80 filings)
PROJECT TO SUBMIT EMERGENCY OPERATIONS PLANS AND RELATED DOCUMENTS UNDER 16 TAC § 25.53 - (71 filings)
BROKER REGISTRATIONS - (65 filings)
CY 2025 FIVE-YEAR REPORTS FOR LINE INSPECTION AND SAFETY UNDER 16 TAC § 25.97 (E) - (55 filings)