Meeting Summary - 07/16/24 RPG Meeting

Grid Monitor AI | Posted 07/16/2024

Related controls:

1 - Antitrust Admonition - Robert Golen

2 - Miscellaneous Updates - Robert Golen

3 - Eastside 345/138-kV Switching Station Project - Robert Golen

  • Robert Golen presented the status update on CPS Eastside 345/138-kV switching station project.
  • CPS submitted the project in February 2024 as a tier one project with an estimated cost of $158 million, targeted for service by June 2028.
  • The project aims to address thermal overloads on 345/138-kV transformers and transmission lines.
  • ERCOT and CPS collaborated on optimal sizing and location of capacitor banks in the San Antonio area.
  • 13 capacitors are planned, mostly in the 50 MVAR block size range.
  • Avoided double counting of transmission upgrades from the San Antonio south reliability two project.
  • Options discussed: Option 1 (CPS proposed), Option 1A (modified), Option 2, and Option 3.
  • No thermal or voltage violations were identified under various conditions.
  • Option 1A, estimated at $47 million, is the preferred and least-cost option.
  • Options 2 and 3 were deemed infeasible due to physical space limitations.
  • ERCOT plans to reclassify the project as a tier three project but has completed tier one evaluations.
  • Sensitivity analysis on generation addition and load scaling showed no material impact.
  • No significant congestion due to this project in the study area.
  • ERCOT recommends Option 1A and will post the EIR to the WMS.
  • No questions were raised at the end of the presentation.

4 - Omicron Reliability Project - Sarah Gunasekera

  • Introduction by Sarah from ERCOT on the CPS Omicron reliability project.
  • Project submitted by CPS to RPG in February; estimated completion by June 2027; cost about $42.5 million.
  • Project addresses thermal and voltage violations at Omicron 138 kV substation.
  • Thermal violations identified on Cagnon to Anderson and Howard to Von Rose lines; voltage violations under n-1, p-3, p-6 conditions.
  • Option 1: CPS proposed five-mile extension from Omicron to Cagnon to Howard 138 kV line; additional 14.3 miles Tally Road to Ranch Town line.
  • Modified Option 1a and 1b: adjusts for duplication issues and includes upgrades.
  • Option 2: Rebuild Casterville to Rafter 138 kV line.
  • Option 3: Rebuild and add line from Castroville to Lytle.
  • Option 4: Convert Castroville 138 kV substation to 345/138 kV.
  • No thermal violations found in assessment, but voltage violations led to addition of 13 capacitors.
  • Cost estimates include capacitor banks; options 1 and 1b preferred for higher load capabilities.
  • Maintenance outage scenario led to three shortlisted options: 1, 1b, and 4.
  • Option 1b chosen as preferred: lowest cost, best long-term load capabilities, least mileage of CCN.
  • Economic benefit identified in upgrading Omicron to Rafter line, included in final recommendation.
  • Projected cost of option 1b: $44.3 million; includes 13 capacitors; omits certain economic upgrades.
  • No further questions in queue; meeting concluded.

5 - Temple Area Project - Tanzila Ahmed

  • Oncor Temple area project submitted in January 2024 for RPG review.
  • Tier one project costing $120.7 million, scheduled for service by May 2026.
  • Addresses thermal violations in Temple area, Bell County due to load growth.

Violations Reported

  • Thermal violations at multiple 138 kV lines and transformers in Temple, Nolanville, Belton, and Killeen areas.
  • Voltage violations in Killeen area.

Shortlisted Options

  • Option 4A: Adding second transformers, new substations, and upgrading lines – cost $257.6 million, ISD December 2028.
  • Option 5A: Similar to 4A with additional components – cost $272.6 million, ISD December 2028.
  • Option 7A: Highest cost, additional new lines – cost $329.3 million, deemed infeasible.

Preferred Option: Option 5A

Rationale

  • Addresses project needs without reliability violations.
  • Least cost option with minimal CCN mileages.

Sensitivity Analysis

  • Load scaling and generation sensitivity analysis showed no material impact.
  • Congestion analysis found no new congestion.

Next Steps

  • Post EIR report by end of month.

  • Recommend project to TAC in July 2024, R&M in August, seek Board approval in August.

Q&A Discussion

Participant: Brian Heathersafe from Brazos Electric

  • Questioned the necessity of a new switching station when existing one could be reconfigured.
  • Response: Existing station deemed inadequate for new connections, further discussion to be taken offline.

7 - Brownsville Area Improvements - Caleb Holland

Project Details:

  • Name: Brownsville Area Improvements transmission project
  • Submission Date: March 2024
  • Tier: Tier One
  • Estimated Cost: $388 million 
  • Estimated In-Service Date: May 2027
  • Issues Addressed: Thermal overloads, Voltage violations
  • Current Status: Under ERCOT independent review

Preliminary Results:

Voltage Violations: 1

Thermal Overloads:

  • P7: 4
  • P6: 1
  • P3: 1
  • P1: 14

Project Options:

  1. Description: Alternative provided by AEP
    • 138 kV single circuit transmission lines
    • 238 kV bus ties at military highway
    • 345/138 kV auto transformers at Palmito
    • Install 300 MVAR Statcom at Chalybe
  2. Description: Preferred option proposed by AEP
    • 345/138 kV auto transformers at Chalybe
    • 22-mile 345 kV double circuit transmission line from Chalybe to Kingfisher
    • 2-mile 345 kV double circuit transmission line from Chalybe to Palmito
    • 2-mile 138 kV single circuit transmission line from Chalybe to Stillman
    • 300 MVAR Statcom at Pompano substation
    • 22-mile 138 kV double circuit transmission line from La Palmo to Stillman
  3. Description: Alternative provided by AEP
    • 345/138 kV auto transformers at Chalybe
    • 22-mile 345 kV double circuit transmission line from Chalybe to Kingfisher
    • 300 MVAR Statcom at Chalybe
    • 138 kV single circuit transmission lines
  4. Description: ERCOT Alternative
    • 345/138 kV three winding auto transformers at Palmito
    • 29.8-mile 345 kV double circuit transmission line from Palmito to Rio Hondo
    • 2-mile 138 kV single circuit transmission line from Chalybe to Palmito
    • 0.4-mile 138 kV single circuit transmission line from Palmito to Stillman
    • 300 MVAR Statcom at Chalybe
  5. Description: ERCOT Alternative
    • Similar To Option: 4
    • Difference: 39-mile 345 kV double circuit transmission line to Palmito from Bonilla
  6. Description: ERCOT Alternative
    • 345/138 kV auto transformers at military highway
    • 345/138 kV three winding auto transformer at Palmito
    • 345 kV substation on the 345 kV double circuit transmission line from north Edinburgh to Kingfisher named Landrum
    • 16-mile 345 kV double circuit transmission line from Landrum to military highway
    • 2-mile 138 kV single circuit transmission line from Chalybe to Palmito
    • 1-mile 138 kV single circuit transmission line from Chalybe to Stillman
    • Replace 238 kV bus ties at military highway
    • 300 MVAR Statcom at Chalybe
    • 138 kV single circuit transmission lines

Shortlisted Options:

  • 2, 4, 5, 6

Next Steps:

  • Continue to evaluate options
  • Provide status updates at future RPG meetings
  • Perform maintenance outage analysis
  • Conduct congestion analysis
  • Perform generation and load scaling sensitivity analyses
  • Conduct subsynchronous resonance assessment
  • Cost estimates and feasibility assessments from transmission service providers
  • Final recommendation by Q3 of this year

8 - Permian Basin Reliability Plan Study - Ying Li

  • Presentation on the Permian Basin Reliability Plan by Ying Li.
  • Study required by Texas House Bill 5066, with PUCT directing ERCOT to develop a plan addressing transmission service and capacity.
  • Timeline: ERCOT will file final reliability plan to the commission in July, followed by stakeholder feedback and commission approval.
  • Ongoing status updates have been presented since January, with a workshop hosted on June 28.
  • Local transmission upgrades and 345-kV import paths for 2030 and 2038 were discussed.
  • Maps and descriptions of local projects provided, majority needed by 2030.
  • EHV import path options for 2038, including 500 kV and 765 kV options, were detailed.
  • Dynamic stability studies indicate no stability issues for 2038 with either 345-kV or 765-kV options.
  • Cost estimates discussed, with 345-kV being the least expensive at around $13 billion compared to 500 kV ($15.3 billion) and 765 kV ($13.8 billion).
  • Comparison of the options with 765-kV deemed the best in terms of efficiency, cost-effectiveness, and operational flexibility.
  • Stakeholder Questions addressed various aspects including transformer inclusion at Hamilton, perceived inconsistencies in load growth projections, choice of specific substations, and transfer capability analyses.
  • Implementation and prioritization of projects depend on PUCT approvals and identified needs.
  • Final report to be filed by July 25th; continuous feedback from TSPs and stakeholders appreciated.

9 - 2024 Regional Transmission Plan - Nelson Avila

  • Nelson Avila presented the 2024 Regional Transmission Plan, focusing on stability interface limits in the Valley region in South Texas.
  • Discussed static and hourly profile limits for various regions, particularly for 2026 and 2029.
  • Highlighted the following GTC limits for 2026 and 2029:
    • Nelson Sharpe Torio Hondo (932 MW, no limit)
    • North Edinburgh to Lowball (1319 MW, no limit)
    • Valley Export (563 MW, no limit)
    • Valley Import (1598 MW, no limit)
  • Mentioned the use of the GQC methodology for the first three limits as posted on the MIS.
  • Discussed non-Valley areas, including North Houston (3712 MW), McAmee Area (3009 MW), West Texas Export (10,404 MW), and Panhandle Region (3239 MW) for both 2026 and 2029.
  • Emphasized non-static hourly profiles and the method to obtain them using historical data and voltage stability analysis software.
  • Questions addressed about the basis for assumed GTC limits in 2029 due to the Lower Rio Grande Valley project.
  • Clarification provided on the West Texas project limits and their relation to economic analysis reports.
  • Explained the reasoning behind excluding thermal-based GTCs like South Texas in the study but mentioned ongoing internal discussions about their future inclusion.
  • No final decisions or actions were concluded; Nelson provided his email for further inquiries.

10 - Adjourn - Robert Golen

Create a free trial account: Sign Up

Grid monitor is free to try. No credit card required


Already have an account? Login

Most Active PUCT Filings

APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (164 filings)

CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (113 filings)

BROKER REGISTRATIONS - (81 filings)

APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE SETEX AREA RELIABILITY PROJECT IN JASPER, MONTGOMERY, NEWTON, POLK, SAN JACINTO, TRINITY, TYLER, AND WALKER COUNTIES - (64 filings)

YEAR-END 2024 ELECTRIC UTILITY EARNINGS REPORTS IN ACCORDANCE WITH 16 TAC § 25.73 - (47 filings)

PROJECT TO SUBMIT EMERGENCY OPERATIONS PLANS AND RELATED DOCUMENTS UNDER 16 TAC § 25.53 - (44 filings)

APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR APPROVAL OF ITS 2026-2028 TRANSMISSION AND DISTRIBUTION SYSTEM RESILIENCY PLAN - (37 filings)