Meeting Summary - 07/16/24 RPG Meeting
Grid Monitor AI | Posted 07/16/2024
1 - Antitrust Admonition - Robert Golen
2 - Miscellaneous Updates - Robert Golen
3 - Eastside 345/138-kV Switching Station Project - Robert Golen
- Robert Golen presented the status update on CPS Eastside 345/138-kV switching station project.
- CPS submitted the project in February 2024 as a tier one project with an estimated cost of $158 million, targeted for service by June 2028.
- The project aims to address thermal overloads on 345/138-kV transformers and transmission lines.
- ERCOT and CPS collaborated on optimal sizing and location of capacitor banks in the San Antonio area.
- 13 capacitors are planned, mostly in the 50 MVAR block size range.
- Avoided double counting of transmission upgrades from the San Antonio south reliability two project.
- Options discussed: Option 1 (CPS proposed), Option 1A (modified), Option 2, and Option 3.
- No thermal or voltage violations were identified under various conditions.
- Option 1A, estimated at $47 million, is the preferred and least-cost option.
- Options 2 and 3 were deemed infeasible due to physical space limitations.
- ERCOT plans to reclassify the project as a tier three project but has completed tier one evaluations.
- Sensitivity analysis on generation addition and load scaling showed no material impact.
- No significant congestion due to this project in the study area.
- ERCOT recommends Option 1A and will post the EIR to the WMS.
- No questions were raised at the end of the presentation.
4 - Omicron Reliability Project - Sarah Gunasekera
- Introduction by Sarah from ERCOT on the CPS Omicron reliability project.
- Project submitted by CPS to RPG in February; estimated completion by June 2027; cost about $42.5 million.
- Project addresses thermal and voltage violations at Omicron 138 kV substation.
- Thermal violations identified on Cagnon to Anderson and Howard to Von Rose lines; voltage violations under n-1, p-3, p-6 conditions.
- Option 1: CPS proposed five-mile extension from Omicron to Cagnon to Howard 138 kV line; additional 14.3 miles Tally Road to Ranch Town line.
- Modified Option 1a and 1b: adjusts for duplication issues and includes upgrades.
- Option 2: Rebuild Casterville to Rafter 138 kV line.
- Option 3: Rebuild and add line from Castroville to Lytle.
- Option 4: Convert Castroville 138 kV substation to 345/138 kV.
- No thermal violations found in assessment, but voltage violations led to addition of 13 capacitors.
- Cost estimates include capacitor banks; options 1 and 1b preferred for higher load capabilities.
- Maintenance outage scenario led to three shortlisted options: 1, 1b, and 4.
- Option 1b chosen as preferred: lowest cost, best long-term load capabilities, least mileage of CCN.
- Economic benefit identified in upgrading Omicron to Rafter line, included in final recommendation.
- Projected cost of option 1b: $44.3 million; includes 13 capacitors; omits certain economic upgrades.
- No further questions in queue; meeting concluded.
5 - Temple Area Project - Tanzila Ahmed
- Oncor Temple area project submitted in January 2024 for RPG review.
- Tier one project costing $120.7 million, scheduled for service by May 2026.
- Addresses thermal violations in Temple area, Bell County due to load growth.
Violations Reported
- Thermal violations at multiple 138 kV lines and transformers in Temple, Nolanville, Belton, and Killeen areas.
- Voltage violations in Killeen area.
Shortlisted Options
- Option 4A: Adding second transformers, new substations, and upgrading lines – cost $257.6 million, ISD December 2028.
- Option 5A: Similar to 4A with additional components – cost $272.6 million, ISD December 2028.
- Option 7A: Highest cost, additional new lines – cost $329.3 million, deemed infeasible.
Preferred Option: Option 5A
Rationale
- Addresses project needs without reliability violations.
- Least cost option with minimal CCN mileages.
Sensitivity Analysis
- Load scaling and generation sensitivity analysis showed no material impact.
- Congestion analysis found no new congestion.
Next Steps
-
Post EIR report by end of month.
-
Recommend project to TAC in July 2024, R&M in August, seek Board approval in August.
Q&A Discussion
Participant: Brian Heathersafe from Brazos Electric
- Questioned the necessity of a new switching station when existing one could be reconfigured.
- Response: Existing station deemed inadequate for new connections, further discussion to be taken offline.
7 - Brownsville Area Improvements - Caleb Holland
Project Details:
- Name: Brownsville Area Improvements transmission project
- Submission Date: March 2024
- Tier: Tier One
- Estimated Cost: $388 million
- Estimated In-Service Date: May 2027
- Issues Addressed: Thermal overloads, Voltage violations
- Current Status: Under ERCOT independent review
Preliminary Results:
Voltage Violations: 1
Thermal Overloads:
- P7: 4
- P6: 1
- P3: 1
- P1: 14
Project Options:
- Description: Alternative provided by AEP
- 138 kV single circuit transmission lines
- 238 kV bus ties at military highway
- 345/138 kV auto transformers at Palmito
- Install 300 MVAR Statcom at Chalybe
- Description: Preferred option proposed by AEP
- 345/138 kV auto transformers at Chalybe
- 22-mile 345 kV double circuit transmission line from Chalybe to Kingfisher
- 2-mile 345 kV double circuit transmission line from Chalybe to Palmito
- 2-mile 138 kV single circuit transmission line from Chalybe to Stillman
- 300 MVAR Statcom at Pompano substation
- 22-mile 138 kV double circuit transmission line from La Palmo to Stillman
- Description: Alternative provided by AEP
- 345/138 kV auto transformers at Chalybe
- 22-mile 345 kV double circuit transmission line from Chalybe to Kingfisher
- 300 MVAR Statcom at Chalybe
- 138 kV single circuit transmission lines
- Description: ERCOT Alternative
- 345/138 kV three winding auto transformers at Palmito
- 29.8-mile 345 kV double circuit transmission line from Palmito to Rio Hondo
- 2-mile 138 kV single circuit transmission line from Chalybe to Palmito
- 0.4-mile 138 kV single circuit transmission line from Palmito to Stillman
- 300 MVAR Statcom at Chalybe
- Description: ERCOT Alternative
- Similar To Option: 4
- Difference: 39-mile 345 kV double circuit transmission line to Palmito from Bonilla
- Description: ERCOT Alternative
- 345/138 kV auto transformers at military highway
- 345/138 kV three winding auto transformer at Palmito
- 345 kV substation on the 345 kV double circuit transmission line from north Edinburgh to Kingfisher named Landrum
- 16-mile 345 kV double circuit transmission line from Landrum to military highway
- 2-mile 138 kV single circuit transmission line from Chalybe to Palmito
- 1-mile 138 kV single circuit transmission line from Chalybe to Stillman
- Replace 238 kV bus ties at military highway
- 300 MVAR Statcom at Chalybe
- 138 kV single circuit transmission lines
Shortlisted Options:
- 2, 4, 5, 6
Next Steps:
- Continue to evaluate options
- Provide status updates at future RPG meetings
- Perform maintenance outage analysis
- Conduct congestion analysis
- Perform generation and load scaling sensitivity analyses
- Conduct subsynchronous resonance assessment
- Cost estimates and feasibility assessments from transmission service providers
- Final recommendation by Q3 of this year
8 - Permian Basin Reliability Plan Study - Ying Li
- Presentation on the Permian Basin Reliability Plan by Ying Li.
- Study required by Texas House Bill 5066, with PUCT directing ERCOT to develop a plan addressing transmission service and capacity.
- Timeline: ERCOT will file final reliability plan to the commission in July, followed by stakeholder feedback and commission approval.
- Ongoing status updates have been presented since January, with a workshop hosted on June 28.
- Local transmission upgrades and 345-kV import paths for 2030 and 2038 were discussed.
- Maps and descriptions of local projects provided, majority needed by 2030.
- EHV import path options for 2038, including 500 kV and 765 kV options, were detailed.
- Dynamic stability studies indicate no stability issues for 2038 with either 345-kV or 765-kV options.
- Cost estimates discussed, with 345-kV being the least expensive at around $13 billion compared to 500 kV ($15.3 billion) and 765 kV ($13.8 billion).
- Comparison of the options with 765-kV deemed the best in terms of efficiency, cost-effectiveness, and operational flexibility.
- Stakeholder Questions addressed various aspects including transformer inclusion at Hamilton, perceived inconsistencies in load growth projections, choice of specific substations, and transfer capability analyses.
- Implementation and prioritization of projects depend on PUCT approvals and identified needs.
- Final report to be filed by July 25th; continuous feedback from TSPs and stakeholders appreciated.
9 - 2024 Regional Transmission Plan - Nelson Avila
- Nelson Avila presented the 2024 Regional Transmission Plan, focusing on stability interface limits in the Valley region in South Texas.
- Discussed static and hourly profile limits for various regions, particularly for 2026 and 2029.
- Highlighted the following GTC limits for 2026 and 2029:
- Nelson Sharpe Torio Hondo (932 MW, no limit)
- North Edinburgh to Lowball (1319 MW, no limit)
- Valley Export (563 MW, no limit)
- Valley Import (1598 MW, no limit)
- Mentioned the use of the GQC methodology for the first three limits as posted on the MIS.
- Discussed non-Valley areas, including North Houston (3712 MW), McAmee Area (3009 MW), West Texas Export (10,404 MW), and Panhandle Region (3239 MW) for both 2026 and 2029.
- Emphasized non-static hourly profiles and the method to obtain them using historical data and voltage stability analysis software.
- Questions addressed about the basis for assumed GTC limits in 2029 due to the Lower Rio Grande Valley project.
- Clarification provided on the West Texas project limits and their relation to economic analysis reports.
- Explained the reasoning behind excluding thermal-based GTCs like South Texas in the study but mentioned ongoing internal discussions about their future inclusion.
- No final decisions or actions were concluded; Nelson provided his email for further inquiries.
10 - Adjourn - Robert Golen
08/14 - 3:00 PM
ERCOT - OTWG Meeting - Webex Only08/14 - 9:00 AM
ERCOT - Texas SET Meeting08/14 - 9:30 AM
ERCOT - LLWG Meeting08/14 - 9:30 AM
08/14/2025
08/13/2025 PWG Meeting08/14/2025
Flexibility as a Service with Octopus Energy US CEO Nick Chaset08/14/2025
Microgrid Market to Reach US$ 163.17 Billion by 2033, Driven by Energy Independence and Rural Electrification08/14/2025
Multidirectional flows of power and information are the grid’s future08/14/2025
How one Texas solar company cut engineering and permitting time from 40 days to fourAPPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (138 filings)
APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (115 filings)
CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (103 filings)
BROKER REGISTRATIONS - (88 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (72 filings)
CY 2024 RETAIL ELECTRIC PROVIDER (REP) ANNUAL REPORTS AND CY 2025 REP SEMI-ANNUAL REPORTS PURSUANT TO 16 TAC 25.107(I) - (57 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR DETERMINATION OF SYSTEM RESTORATION COSTS - (46 filings)