4 - Technical Advisory Committee Update - John Schatz
RMGRR177 was approved.
RMS ROS, and WMS 2024 goals were approved
Lubbock update was provided and there were no questions, indicating satisfaction with Lubbock's transition progress
TAC meeting centered around significant discussion on NOGRR245, with multiple failed ballots, eventually passing as recommended by ROS in the 9/14/23 ROS Report as amended by the 3/22/24 Joint Commenters 2 comments as revised by TAC
NPRR1212 and PGRR114 are linked RRs that clarify relationship between DSPs and REs in terms of providing ESI IDs before the RE can start consuming load
Consensus to move NPRR1212 to the combo ballot with an attached motion that RMS endorse NPRR1212 as recommended by PRS in the 03/20/24 PRS comment.
Lubbock Power and Light's transition to a TDSP is complete
LP&L working through issues related to metering and continues to make progress addressing those
9 - Lubbock Retail Integration Task Force - Sheri Wiegand
Discussed the transition stacking logic, removed on March 4, to accommodate true move-ins and choice transactions.
Have made progress addressing issues related to transition to competitive REPs taking over billing, multiple ESI IDs for the same address not all enrolling with the same REP and addressing low meter read rates associated with a server crash during 3/4-3/19